Ask the Experts: Hammock Tasks 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
Project Portfolio Management: Align Project Resources with Business Strategy
Team Players: Exchanging Project Data with Your Development Team
Ask the Experts: A Successful EPM Implementation Has More than Technology
Dealing With Uncertainty in Project Schedules
Microsoft Project Options you want to know about
Performance Tuning Your Scheduling Practices
Project Options You Want to Know About
Microsoft Community Leader Award Winners
8 Important Lessons I Learned During EPM Implementations
Insights for Scheduling
Creating an Agile Schedule with MS Project
Ask the Experts: Similar Task Names
Habits: Why Trader Joe’s Serves Free Coffee Every Day of the Year
Toolbar and Menu Commands for Microsoft Project 2007
 
 

Danielle of McLeansboro, IL asks: I hire flat amount contractors to perform multiple tasks. What is the best way to keep track of the schedule and the contract costs? We know that the contract amount will increase during the life of the contract. Since the contracts are flat amounts, we're not concerned with updating hours per task but would like to track the schedule progress. The resources aren't named resources, and the contractor will vary the workers and manage the day-to-day resource schedule. The tasks are varied calendar-wise with some tasks being assigned as five days, six days, or seven days per week schedule.

Ellen answers: Solving this problem takes a few steps, but it's doable. You have a lot going on in your requirements so let's take it one step at a time.

First, flat amount contract values

Contractors have a flat amount contract covering the cost of multiple tasks. Dividing up cost per task isn't possible for your situation, so you need a way to have costs apply to a section of work. You might consider setting up a hammock task for the task grouping to hold the cost and then creating the schedule task detail to manage the work. A hammock task is a task that spans the length of a summary task and usually carries work that would apply to all tasks contained in the summary section of work. Hammock tasks may also be used to hold costs.

Second, not concerned about number of hours of work but need to manage schedule

You also will need to manage the schedule of the tasks that the flat amount contract applies to. This could be handled in detail tasks underneath the hammock task. Assigning a resource to the task will help in the scheduling of the task.

Third, task schedules can be five, six, or seven days depending on the task needs

To help with the unique scheduling that you require, you'll also need a few new calendars that will be used as task calendars to create unique timeframes.

The steps to accomplish the above requirements are described below:

1. To accomplish the resources' varied schedules, create a five-day, six-day, and seven-day calendar. These will be used as task calendars to establish unique timeframes for tasks. Project | Change Working Time in Microsoft Project 2010 or- Tools | Change Working Time in earlier versions,

2. Create a resource to be used to assign the work to the tasks. In this example the contractor's name is Smith. Create a "Smith - Work" work resource for the contractor and assign the five-day calendar to the resource on the Resource Sheet. The number of hours of work isn't a concern since the company doing the work will manage the day-to-day schedule for the resources.

3. Create a "Smith - Cost" resource on the Resource Sheet, which will be used hold the contract and cost when assigned to the hammock task. An example of the entered resources is shown in Figure 1.

Lehnert Figure 1

4. In the schedule on the Gantt chart create a summary task section for the work included in the flat amount contract. Build out the details of the tasks, applying duration, relationships, constraints, deadlines, etc.

5. Above the detail tasks for the summary grouping underneath the summary task create another task that isn't linked to the other tasks. This will be the hammock task for the summary group of work. Adjust the duration of the hammock task to the total length of the summary but not longer than that. If the hammock task is longer than the summary task, the hammock becomes the critical path for the section of work. The hammock task is indicated in the red box in the example in Figure 2.

Ellen Lehnert Figure 2

6. Assign the cost resource to the hammock task with the cost value of the contract. Then assign the work resources to the detail work tasks.

7. Add task calendars to override resource calendars and adjust the schedule for the six-day and seven-day unique timeframes where needed. To assign a task calendar to a task and override the resource calendars, do this: Double click on the task to open the Task Information box | Advanced tab | Task calendar; and place a check mark in the box to the left of Scheduling Ignores Resource Calendar selected. An example and instructions are shown in Figure 3.

The activities, "Replace carpeting," "Spruce up the yard," and "Repair Roof," have task calendars assigned.

Lehnert Figure 3

The advantages of using this approach are several:

  • You don't have to break up a flat amount contract over multiple tasks.
  • You can track the work on each task using percent complete. More work or duration may be added if necessary to the detail tasks.
  • Since cost is held on the hammock task, the cost won't be affected.
  • When managing the project, if the tasks take longer than planned, you can increase the length of the hammock, but the cost value will remain the same. You can also update the hammock task with percent complete. The length or the task won't affect the project schedule but could affect cost accrual for actual cost.
  • If the cost increases, the Cost Resource amount assigned to the hammock task can be increased.

Tip: The Gantt chart will display the contract values for the contractors next to the contractor's name. If you would like to hide the contract values, consider entering the full Resource Name in the Resource Initials field on the Resource Sheet. Then replace Resource Initials for Resource Name in the Gantt chart view. You would still see the resource assigned to the task, but the cost values would be hidden.

To copy the Resource Name column to the Resource Initials column:

1. Display the Resource Sheet.
2. Click on the column header Resource Name.
3. Click Copy.
4. Click on the column header Resource Initials.
5. Click Paste.

To replace the Resource Names with Resource Initials on the Gantt chart:

1. Display the Gantt chart you would like to change.
2. Right click on the right side of the view and select Bar Styles.
3. Select the Task blue bar in the top pane.
4. Select Text in the bottom section of the box.
5. Click on the arrow next to "Resource Names" and select Resource Initials.
6. Click OK to close the box.

Ellen Lehnert

With over 20 years of corporate training experience, Ellen Lehnert, MVP, PMP, MCT, MCITP, is a specialist in Microsoft Project and Microsoft Project Server. She's the co-author of "Managing Projects with Microsoft Project 2010 Desktop," published and available for puchase through MVP-Press. Ellen brings a unique combination of licensed teacher and programming background to the classes she teaches as well as process development, installations, and consulting. Contact her at ellen@lehnertcs.com or at LehnertCS.

Do you have a question for our experts? Send that to editor@mpug.com. 

 