Ask the Experts: Updating the Baseline 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
Project Portfolio Management: Align Project Resources with Business Strategy
Team Players: Exchanging Project Data with Your Development Team
Ask the Experts: A Successful EPM Implementation Has More than Technology
Dealing With Uncertainty in Project Schedules
Microsoft Project Options you want to know about
Performance Tuning Your Scheduling Practices
Project Options You Want to Know About
Microsoft Community Leader Award Winners
8 Important Lessons I Learned During EPM Implementations
Insights for Scheduling
Creating an Agile Schedule with MS Project
Ask the Experts: Similar Task Names
Habits: Why Trader Joe’s Serves Free Coffee Every Day of the Year
Toolbar and Menu Commands for Microsoft Project 2007
 
 

Rick from San Jose, CA asks: During the execution of my project, my baseline needs to be updated because of change requests from my clients. What is the best way to do this in Microsoft Project?

Answer: When the baseline of the project is set, it is set for all three areas of the data structure. Values will be set for tasks, assignments, and resources. There are technically 11 sets of baseline fields in the system, Baseline and Baselines 1-10. The Baseline field is the default used when you first set a baseline. When a baseline is updated, you select one of the other 10 sets of Baseline fields.

By default the Baseline fields will be used in the project variance calculations. Baseline fields 1-10 are used for earned value, updated baselines, or as free use fields for schedulers. If updated baselines are updated to use fields Baseline 1-10, the option to indicate an alternate baseline used for variance calculations should be set.

When setting a baseline, the fields in the first column of Table 1 will be copied and held in the fields in column two. The "estimated" fields are used for manually scheduled tasks in Project 2010:

 Field   Copied to
 Work   Baseline Work
 Cost   Baseline Cost
 Duration  Baseline Duration
 Start   Baseline Start
 Finish   Baseline Finish
 Start   Baseline Estimated Start
 Finish   Baseline Estimated Finish
 Duration   Baseline Estimated Duration

If changes to the project schedule are approved and the customer agrees on the setting of a new baseline, follow the steps below. In the example, the baseline will be saved into the Baseline1 fields. Baselines 1-10 are available for this purpose:

1. Set the baseline to the Baseline1 fields.
2. Change the option to indicate which baseline should be used for the variance calculation.
3. Change a Gantt Chart View to display Baseline1 fields.
4. Change the Variance tables to view the Baseline1 fields.

Step 1

To set the baseline to the Baseline1 fields in Project 2010:

1. Project | Set Baseline | Set Baseline.
2. Set Baseline -- Baseline 1.
3. For Entire Project.
4. Click OK.

To set the baseline to the Baseline1 fields in earlier Project versions:

1. Tools | Tracking | Set (or Save) Baseline.
2. Set Baseline -- Baseline 1.
3. For: Entire Project.
4. Click OK

Step 2

To change the option to indicate which baseline should be used for the variance calculation in Project 2010:

1. File | Options | Advanced | Earned Value option for this project.
2. Select Baseline 1.
3. Click OK to close the box.

Lehnert Figure 1

To change the option to indicate which baseline should be used for the variance calculation in earlier Project versions:

1. Tools | Options | Calculations | Earned Value.
2. Click on the Baseline for Earned Value calculations and select Baseline1.
3. Click Close.

Lehnert Figure 2

Step 3

To change a Gantt Chart View to display Baseline1 fields in Project 2010:

1. Display a Gantt Chart View.
2. Format | Baseline | Baseline1.

Figure 3

To change a Gantt Chart View to display Baseline1 fields in earlier Project versions, select a view to copy. It will be easier if you select one that already is using displaying the baseline. In the example below, a copy of the Tracking Gantt view will be changed:

1. Best Practice -- copy the Tracking Gantt and change the copy.
2. View | More Views | Tracking Gantt | Copy.
3. Rename the view "Tracking Gantt using Baseline1."
4. Click Show in the Menu.
5. Click OK.
6. Click Apply

To change the formating to see the Baseline1 fields:

1. Format | Bar styles.
2. Change the From and To columns for the Baseline fields to Baseline1 Start and Baseline1 Finish. (See the figure below.) Scroll down and change the values of the rollup baseline fields if using rolled up task bars.
3. Click OK to close the box.

Lehnert Figure 4

Step 4

Change the Variance tables to view the Baseline1 fields works the same in all versions of Project.

1. Right click in the upper left corner above the ID numbers and select Variance.

Figure 5

2. Double click on the column heading Baseline Start.
3. Select Field Name Baseline1 Start.
4. Click OK if you're using a version earlier than Project 2010.
5. Double click on the column heading Baseline Finish.
6. Select Field Name Baseline1 Finish.
7. Click OK if you're using a version earlier than Project 2010.

The Variance Table and Gantt Chart View using the Baseline field values are displayed in the figure below. Baseline Start and Baseline Finish display for Baseline values. Note the values in the Variance columns:

Figure 6

Changes in the schedule were made and the baseline was set using the Baseline1 fields. The Variance Table and Gantt Chart View displaying the Baseline1 field values are shown below. Note the changes to the Start and Finish Variances and Gantt bars. Baseline1 Start and Baseline1 Finish are used to display the baseline dates. Note the values in the Variance columns.

Figure 7

Each baseline is dated by the date the baseline was set to keep a history of the baselines used during the execution of a project. It's also advantageous to create Gantt Views that display multiple baselines for comparison. The Multiple Baseline Gantt view is preset to display Baseline, Baseline1, and Baseline2 for this purpose.

Ellen Lehnert
With over 20 years of corporate training experience, Ellen Lehnert, PMP, MCT, MCITP, is a specialist in Microsoft Project and Microsoft Project Server. She’s currently preparing a curriculum for Project 2010, titled, “Managing Projects with Microsoft Project 2010 Desktop.” Ellen brings a unique combination of licensed teacher and programming background to the classes she teaches as well as process development, installations, and consulting. Contact her at ellen@lehnertcs.com or at