Certification Insider: Managing Multiple Projects 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
Project Portfolio Management: Align Project Resources with Business Strategy
Team Players: Exchanging Project Data with Your Development Team
Ask the Experts: A Successful EPM Implementation Has More than Technology
Dealing With Uncertainty in Project Schedules
Microsoft Project Options you want to know about
Performance Tuning Your Scheduling Practices
Project Options You Want to Know About
Microsoft Community Leader Award Winners
8 Important Lessons I Learned During EPM Implementations
Insights for Scheduling
Creating an Agile Schedule with MS Project
Ask the Experts: Similar Task Names
Habits: Why Trader Joe’s Serves Free Coffee Every Day of the Year
Toolbar and Menu Commands for Microsoft Project 2007
 
 

The Project Server 2007 certification exam is jammed with questions about managing multiple projects, which is no surprise. But desktop Project has features for managing more than one project without Project Server, and the 2007 Project exam, 70-632, tests you on them. This month I run you through Project's multi-project features, when to use them, and how to make them behave the way you want.

Sometimes a link between a task in one project and a task in another is all you need. For example, you're setting up the new accounting system for your company and the only thing you want from the marketing department's publicity project is the new corporate logo. An external task dependency is a link from a task in a different project to a task in the current project.

When you can create an external task dependency in the Task Information dialog box, the only difference is that you first type the name of the external project, a backslash (\), and then the task ID.

In desktop-Project land, a master project is a more robust way to manage several projects. You create a Project file to act as the master and insert each individual Project file into the master file. A master project works for the following situations:

  • A project has several subprojects, each handled by a different project manager, for example, the marketing events your company is hosting. The subproject managers can each work on their own Project files, while you look at the big marketing picture by opening the master project and examining all the tasks in all the subprojects.
  • Several projects share the same resources. If you add all the projects to a master project and use a resource pool, you can see all the resource assignments across all the projects to ensure that your resources aren't overallocated.
  • You juggle several small projects, and want to look at or work on all your projects at the same time. You can insert projects into a master file to create consolidated views and reports.

Here are some key features of master projects:

  • Inserted subprojects appear in one Project window, so you can work on them and save them all at once as if they were a single file.
  • Inserted projects look like summary tasks that you can expand or collapse depending on the level of detail you want.
  • You can do anything with subproject tasks within the master project that you can do in individual files.
  • A master project is a regular Project file, so you can add tasks to it, such as a task for your supervision of the project managers working on the subprojects.
  • Changes made to a subproject appear immediately in a master file, if it's open and you insert the subproject with the "Link to project" checkbox turned on. If you make a change to a subproject from the master project, those changes appear in the subproject file.

Master project files are regular Project files. Simply create a new blank project. Then, in Project 2007, choose Insert on the main menu and choose Project. In Project 2010, click the Project tab, and in the Insert group, click Subproject. In the Insert Project dialog box, select the project you want to insert, make sure the "Link to project" checkbox is turned on, and then click Insert. Turning on the "Link to project" checkbox tells Project to update the master project whenever the inserted project changes.

Task ID numbers in a master project aren't very helpful. Project assigns sequential ID numbers to each subproject starting with the number 1. But, the tasks within inserted projects still use their original ID numbers. So, you'll see several tasks with the same ID number. In a master project, it's best to use the WBS code to identify tasks -- and use a WBS code that has a project prefix.

Another way to identify tasks and resources from different subprojects is with the Subproject File field. Simply insert this field into your Gantt chart table, and you'll see the file paths and filenames for inserted projects.

Biafore Figure 1

If you manage several small projects, chances are good the projects share the same resources. Project Server has cool tools for finding and sharing resources; but you can share resources with desktop Project, too. The key is creating another regular Project file dedicated to holding the information about your shared resources. Then you apply this so-called resource pool to the projects that share resources so you can see and manage assignments across all the projects connected to the pool.

The best way to set up a resource pool is to create a new Project file that does nothing but act as a resource pool. If you use a Project file with tasks in it as the resource pool, you may hit conflicts if you want to work on your project and someone else wants to work on resource information. When you save the Project file, name it something like MyResourcePool, so you know that it's only for resources.

To use resources from a resource pool, you have to link your project file to the resource pool. Project files that use a resource pool are known as sharer files. To link a project to the resource pool, open the resource pool as read-only. (That way, you don't lock others out of the file.)

1. Open the Project file you want to link.

2. In Project 2007, click Tools on the main menu, and then choose Resource Sharing | Share Resources. In Project 2010, on the Resource tab in the assignments group click Resource pool and then click Share Resources.

3. Select the "Use resources" option, and in the From drop-down list choose the resource pool.

4. In the "On conflict with calendar or resource information" section, the best choice is to let the resource pool take precedence. That way, your resource pool is always your trustworthy source for shared resource information, whether you share the resources among your projects or with other project managers.

5. Click OK to complete the connection to the pool.

When you open a sharer file, Project asks whether or not you want to open the resource pool. You usually want to open the resource pool, so you can see all the resources from the resource pool and shared resource assignments from all sharer files. To open the resource pool, select the "Open resource pool to see assignments across all sharer files" option.

Opening the resource pool also means that your resource assignments affect the resource's availability in the resource pool. When you save a sharer file with the resource pool open, Project asks if you want to update the resource pool. To save the resource changes to the resource pool, click OK.

To get the most recent changes from the resource pool, you can refresh the pool info. In Project 2007 click Tools on the main menu, then choose Resources Sharing and click Update Resource Pool. In Project 2010, on the Resource tab in the Assignments group click Resource Pool and then click Refresh Resource Pool. Project immediately shows the most current information from the resource pool. You can update the resource pool immediately using the Update Resource Pool command (on the Resource Sharing submenu in Project 2007 and in the Resource Pool drop-down menu in Project 2010).

When you open a resource pool after it's connected to at least one sharer file, you have three choices for how to open the pool. These options seem to be a favorite topic for Project certification tests, so pay attention.

  • Read-only is usually the one you want. The "Open resource pool read-only allowing others to work on projects connected to the pool" option opens the resource pool as read-only so every project that uses the resource pool can access the pool at the same time. Although the resource pool is opened as read-only, saving a sharer files updates the resource pool with resource assignment information.
  • Read-write is for changing resource values. If you have to make changes to resources in the resource pool, select the option, "Open resource pool read-write so that you can makes changes to resource information (like pay rates, etc.), although this will lock others out of updating the pool with new information." That way, you can modify resource fields like costs and resource calendars. No one else can access the resource pool, so work quickly, save the resource pool file, and close it.
  • Create a master project with all the sharer files and the resource pool. The option "Open resource pool read-write and all other sharer files into a new master project file…" combines the resource pool and all sharer files into a brand-new master project. This is an easy way to build a master project to work on or to produce reports. The resource pool is read-write, so other project managers can't open their sharer files connected to the resource pool.

Think You Know How to Manage Multiple Projects? Test Yourself!

You manage several projects that use the same resources. You have to make sure the resources aren't overallocated and also track progress for all the projects. Your manager has assigned to assistants to help manage your projects. How can you track overall progress while your assistants work on their individual Project files (using Project 2007)?

A: Create a master project and use the Project command on the Insert menu to insert all Project files into the master project.

B: Create a master project and use the Project command on the Insert menu to insert all Project files into the master project. In the Insert Project dialog box, click the down arrow on the Insert button and then choose Insert Read-Only.

C: Create a master project and use the Project command on the Insert menu to insert all Project files into the master project. When you open the master project, choose the option to open the files read-only.

D: Create a master project and use the Project command on the Insert menu to insert all Project files into the master project. When an assistant begins work on a project, select the summary task for the inserted project and click the Task Information icon on the Standard toolbar. On the Advanced tab, turn on the "Read only" check box. Click OK and save the master project and inserted projects.

No peeking! Scroll below the book ordering information to read the answer to this quiz.


A Special Note from Bonnie!

Dear Readers,

I'm updating my Microsoft Press project management book, newly titled, Successful Project Management. I am looking for tips and best practices for successful project management (and using Microsoft Project to manage successfully) from a variety of project managers in a variety of industries. Real-world examples or anecdotes to illustrate points would be ideal.

I can provide an outline of potential topics for tips and best practices based on the previous edition of the book, but topics that correspond to trends and recent events are great, too (such as working with global teams, risk management, financial oversight, demographics within the workforce, for example).

Each contributor whose best practice is included in the book will get an acknowledgment in the book and a copy of one of my project management books or DVDs. In addition, I will have a project management blog this winter and will include acknowledgements on the blog, links to contributors' Web sites, and an invitation to be a guest blogger.

Want to know more? Email Bonnie at bonnie.biafore@gmail.com.


Order the the MCTS Self-Paced Training Kit (Exam 70-632): Managing Projects with Microsoft Office Project 2007.

To learn more about Microsoft certification, read, "Microsoft Project Management Certification: How to Get Started."

Read Microsoft's exam topics list for 70-632 here.

Author Bonnie Biafore


Bonnie Biafore is the author of O'Reilly's Microsoft Project 2010: The Missing Manual and Microsoft Press' On Time! On Track! On Target! Managing Your Projects Successfully with Microsoft Project. She's developing a Project 2010 course for lynda.com. As a consultant, she manages projects for clients and wins accolades for her ability to herd cats. You can learn more at Bonnie's website or email her at bonnie.biafore@gmail.com. 


The Answer to Test Yourself!

A is incorrect. Inserting a Project file into a master project inserts it as read-write. If you open the master project, no one can open the inserted subproject.

C is incorrect. There is no option to open inserted projects as read-only.

B and D are correct. You can insert a project as read-only or change it to read-only after you have inserted it into a master project. By inserting a project as read-only, Project opens the file as read-only, so you can view the project while someone else has the file open. In addition, you can only edit the inserted project by opening its Project file directly. 