Certification Insider: Microsoft Project Budgets and Costs 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
Project Portfolio Management: Align Project Resources with Business Strategy
Team Players: Exchanging Project Data with Your Development Team
Ask the Experts: A Successful EPM Implementation Has More than Technology
Dealing With Uncertainty in Project Schedules
Microsoft Project Options you want to know about
Performance Tuning Your Scheduling Practices
Project Options You Want to Know About
Microsoft Community Leader Award Winners
8 Important Lessons I Learned During EPM Implementations
Insights for Scheduling
Creating an Agile Schedule with MS Project
Ask the Experts: Similar Task Names
Habits: Why Trader Joe’s Serves Free Coffee Every Day of the Year
Toolbar and Menu Commands for Microsoft Project 2007
 
 

Budgets can make or break a project, and, as it turns out, could be the difference between pass or fail on the Project certification test. So it's no surprise that controlling costs tests your prowess as a project manager and as a Microsoft Project maven. This column reviews several cost-related features in Project, because knowing the right feature for the job is a big part of answering test questions correctly.

In Project, it all starts with costs associated with resources, as you learned in my previous article, "Certification Insider: Resourcing Project Plans." Project calculates task costs based on the rates and other expenses associated with the resources assigned. (Remember, you set the cost for a cost resource when you assign it to a task.) After the project begins, Project recalculates forecasts to incorporate actual costs for the work performed.

Viewing Costs

Whether you're up to your elbows in planning or watching progress like a hawk, you can view cost information with a plethora of Project features. A snapshot of the bottom line is a good place to start when management has given you a price tag and you want to see whether the estimated cost is on target.

  • The project summary task rolls up the costs for all tasks into an overall total. The project summary task takes the pole position in the first row of the project task list. With a task-oriented view visible, on the Format tab, in the Show/Hide group, turn on the Project Summary Task checkbox. Apply the Cost table.
  • The Project Statistics dialog box shows bottom-line project information, such as when the project starts, when it's forecast to finish, how much work it requires, and the cost estimate. On the right side of the File tab, click Project Information, and then click Project Statistics. The Cost cells show the current forecasted cost (Current), baseline cost, actual cost so far, and the remaining cost.
  • The Project Summary text-based report shows the same information available in the Project Statistics dialog box, but you can print the report more easily.

After you see the big picture, you probably want to check out task and assignment costs to find ways to reduce the project price tag.

  • Task cost: Apply the Cost table to a task view.
  • Resource cost: Display the Resource Sheet and then insert the Cost field in the table. The Cost value for a resource is the total cost for all of the assignments for the resource. This technique is a slick way to see how much you're spending for cost resource, such as travel or training.
  • Assignment cost: Display the Task Usage view or Resource Usage view and apply the Cost table. The Cost field in an assignment row represents the cost for the individual assignment. The cost in the resource name row is the total cost for all assignments for the resource. In the Task Usage view, the cost in the resource name row is the cost for the assignment. The cost in the task name row is the total cost for the task.

Comparing Costs with Your Budget

Project's budget resource feature lets you define a budget for different categories of expenses. You can compare your budgeted costs to your scheduled costs to see whether your project costs are toeing the line by category.

Budget resources make quick work of comparing the budget to planned costs for cost resources. For work resources, you enter budgeted work amounts, not costs, so you can't accurately compare labor costs to a budgeted value.

Setting up a project to use the budget resource feature is a multi-step process:

1. Create budget resources and designate them as such. Create the resources in the Resource Sheet. In the Type field, choose Work, Material, or Cost. In the Resource Information dialog box, on the General tab, turn on the Budget checkbox.

Tip! Name budget resources so you can identify them as such. If you start budget resource names with a number, they appear at the top of a resource list that's sorted alphabetically from A to Z.

2. Assign the budget resources to the project summary task. A budget resource represents the overall amount for an expense category for an entire project. That's why you assign them to the project summary task, not individual tasks. Use any method for assigning resources that you prefer. (Try as you might, you can't assign a budget resource to anything except the project summary task.)

3. Associate work, material, and cost resources with their budget type. You have to tell Project which work, material, and cost resources go with each budget category. You can use a text field or the Group or Code fields in the Resource Sheet. For every resource in the Resource Sheet (including budget resources), fill in the Group, Code, or text field with the name of the Budget category. That's how you link resource costs and budget costs.

4. Enter budgeted cost and work amounts for budget resources. You can enter budget totals for the entire project in the Task Usage view. You add the values to the project summary task, which sits conveniently at the top of the list. Insert the Budget Cost field and Budget Work field to the table. If you want to enter budget values by time period, add the Budget Cost and Budget Work fields to the time-phased portion of the view (using the Detail Styles dialog box).

5. Group resources in the Resource Usage view to compare budget cost and work with planned values. Set up a table to show budgeted (Budget Cost and Budget Work) and planned fields (Cost and Work). Group the view by your budget categories, as shown in the figure. With the Resource Usage view grouped by budget category, each group includes one budget resource and the work, material, and cost resources that apply to that budget category. In the group summary row, compare the Budget Cost or Budget Work values to the Cost or Work values.

Figure 1. To pass the Project 2007 exam, you'd better know how to categorize costs by budget category.

Biafore figure 1

Think You Know Budgets and Costs? Test Yourself!

You use several contractors for your project and the management team has given you a budget for external resources and travel. You want to compare your planned costs with the budget values you've been given. Which of the following steps help you achieve your goal?

A: Use a custom text field to associate each resource in your Resource Sheet with a budget category.
B: Create a custom cost field to store the budgeted costs for each task.
C: Create a cost resource for each budget category.
D: Create budget resources for work and cost.

No peeking! Scroll below the book ordering information to read the answer to this quiz.


Order the the MCTS Self-Paced Training Kit (Exam 70-632): Managing Projects with Microsoft Office Project 2007.

To learn more about Microsoft certification, read, "Microsoft Project Management Certification: How to Get Started."

Read Microsoft's exam topics list for 70-632 here.

Author Bonnie Biafore


Bonnie Biafore is the author of O'Reilly's Microsoft Project 2010: The Missing Manual and Microsoft Press' On Time! On Track! On Target! Managing Your Projects Successfully with Microsoft Project. She's developing a Project 2010 course for lynda.com. As a consultant, she manages projects for clients and wins accolades for her ability to herd cats. You can learn more at Bonnie's website or email her at bonnie.biafore@gmail.com. 


The Answer to Test Yourself!

A custom cost field doesn't let you link resources to budget categories. A cost resource is a type of resource that represents project costs, not budgeted values. Instead, you create budget resources in Project and associate them with the other types of resources to compare budgeted and planned values. The correct answers are A and D.