Certification Insider: Resource Overallocations 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
Project Portfolio Management: Align Project Resources with Business Strategy
Team Players: Exchanging Project Data with Your Development Team
Ask the Experts: A Successful EPM Implementation Has More than Technology
Dealing With Uncertainty in Project Schedules
Microsoft Project Options you want to know about
Performance Tuning Your Scheduling Practices
Project Options You Want to Know About
Microsoft Community Leader Award Winners
8 Important Lessons I Learned During EPM Implementations
Insights for Scheduling
Creating an Agile Schedule with MS Project
Ask the Experts: Similar Task Names
Habits: Why Trader Joe’s Serves Free Coffee Every Day of the Year
Toolbar and Menu Commands for Microsoft Project 2007
 
 

If you overload resources, your project finish date may look good, but it's probably bogus. Assigning 20-hour work days doesn't mean your team members will stay up that long and work that hard. The secret to success is to balance workloads so resources are busy, but not burning out. This month, you learn how to spot overallocations and balance workloads on your own, a topic covered in Microsoft's Project certification exam, 70-632.

Finding Overallocations

The first step to a well-balanced schedule is finding resource overallocations. Resource and assignment views are your best bet. Here's a quick rundown of the best views for optimizing assignments.

The Resource Sheet provides a sneak peak at overallocations. If a resource is overallocated at least once during the project, the text in the resource's row is bold and red, and the Indicators column displays a yellow diamond with an exclamation mark. But this view doesn't say when, how much, or on which assignments the overallocations occur.

The Resource Usage view combined with the Resource Graph is a one-two punch for knocking out overallocations. It shows the hours assigned by assignment and period while the Resource Graph makes it easy to see which periods are overallocated. The left pane of the Resource Usage view has a summary row for each resource with the task assignments below. The timescale shows the assigned hours by period. Overallocated resources appear in bolded red text. Hours that exceed the resource's maximum available time appear in red, too. If several tasks contribute to an overallocation, the individual task hours may be black, but the total hours in the resource row are red, as you can see in Figure 1.

Figure 1. The Resource Graph showing overallocation.

Biafore Figure 1

The Resource Graph shows allocation over time, resource by resource. A vertical bar shows the selected resource's allocation during one time period. A horizontal line shows the resource's maximum units. When the vertical bar is higher than the horizontal line and part of the bar is bright red (the overallocation), the resource is overallocated.

Sometimes resources are overallocated for a day or so, but can finish the job by the end of a week. Increase the length of the timescale periods (for example, from days to weeks) to see whether overallocations work themselves out. (Right-click the timescale heading to modify the timescale settings.)
After you find an overallocation, you can show other values in the Resource Graph such as Work or Remaining Availability. For example, switch to Remaining Availability to find someone to take some hours. Right-click the Resource Graph timescale, and then, from the shortcut menu, choose the field you want to display in the graph.

Tip: To emphasize overallocations in any resource-oriented view, turn on the Overallocated Resources filter, which displays only resources that are overallocated at some point during a project.

The Resource Allocation view displays the Resource Usage view in the top pane and the Leveling Gantt in the bottom pane, so you can delay tasks to resolve overallocations as you'll learn shortly.

Balancing Workloads

The easiest way to eliminate overallocations is to ask resources to work longer hours. This approach is realistic only when overallocations are small and don't last too long (no more, say, than 20 percent and two weeks).

To officially schedule longer days so assignments don't show up as overallocations, don't change a resource's maximum units in the Resource Sheet. Maximum units represent the percentage of the standard workday that the resource devotes to the project. Modify the resource's calendar to set up a special workweek or exception to reflect the short schedule change.

Replacing a resource with someone with more time (or adding additional resources) is the next best thing. You can reassign only the overallocated hours or an entire assignment. The Assign Resources dialog box makes it easy, because you can look for resources with the right characteristics or enough free time to complete the assignment. Click the plus sign to expand the Resource list options. Then apply a filter to find the type of resources you want or type the number of available hours you're looking for.

In a task view like the Gantt chart or Leveling Gantt, select the task you want to reassign. In the Assign Resources dialog box, the assigned resources for the selected task appear at the top of the list preceded by a checkmark. To reduce a resource's assignment, type the new percentage in the Units cell (from 100 percent to 50 percent, for example). To add a resource to the task, type the percentage you want to assign in the new resource's Units cell and then press Enter. To replace a resource completely, select the one you want to replace and click Replace. In the Replace Resource dialog box, select the new resource and click OK.

Another way to eliminate overallocations is to delay one or more tasks so that assigned resources can work on the tasks one after the other. Project offers two types of delays:

  • Leveling delay applies to tasks and pushes the start date for the entire task. The table in the Leveling Gantt view includes the Leveling Delay field. To delay a task, type the length of delay in the Leveling Delay cell. (You can type a value like 3d to delay a task by three days. Project changes the durations you enter into elapsed time, so 3d turns into 3 "edays".) In the Leveling Gantt chart, Project shows leveling delays that you've added by a thin line at the start of a task. You can remove all leveling delays by choosing Tools | Level Resources, and then clicking Clear Leveling.

Note: A leveling delay isn't the same as lag time. Lag time is a period you need to wait between tasks, for example, an hour for paint to dry before you start the second coat.

  • Assignment delay is a delay on an individual assignment for a task, so some of the resources start working right away while others start a bit later. To add assignment delays to tasks, display the Resource Usage view and add the assignment Delay column to its table. Or in the Task Entry form, right-click the table area and choose Resource Schedule. The Delay column represents the Assignment Delay field.

Project optimistically assumes that resources work at the same level from the start to the finish of every task. To reflect how work really gets done, you can apply work contours to assignments. Like a sculptor, a work contour carves the level of effort that's assigned over the duration of an assignment. Tasks tend to ramp up in the beginning, run at their peak in the middle, and then taper off at the end. Work contours reduce the hours for some time periods, so they extend assignment and task duration.

The Flat contour, which is the default setting, schedules the same hours of work each day of an assignment. The other contours have high and low points; the highs matching the number of hours in a day as a Flat contour. The names for work contours make sense. Back Loaded starts off slow and pushes the effort toward the end of the task. The Bell contour ramps up to a peak like the Back Loaded contour and then trails off like Front Loaded contour. The Turtle has low levels at the beginning and ends with a full load in the middle.

To apply a work contour to an assignment, display an assignment view like Resource Usage. Double-click the resource assignment you want to contour. In the Assignment Information dialog box, on the General tab, choose the contour in the Work Contour list (see Figure 2) and click OK. The Indicators column in a view table displays an icon for the applied contour.

Note: If resources cost more for overtime, you can assign work hours specifically as overtime in the Overtime Work field. Keep in mind, Project doesn't automatically switch hours past the normal workday to overtime hours, so tracking overtime in the program is tedious at best. Use overtime only when resources cost more for overtime work. Project calculates the cost of overtime work hours by multiplying those hours by the Overtime Rate in the resource's record.

Figure 2. Applying a black loaded contour.

Biafore Figure 2

Think You Know Resource Overallocations? Test Yourself!

One of the resources on your project is overallocated. After you celebrate your good fortune, you want to delay the tasks that resource works on to eliminate the overallocations. What's the best way to do that?

Answer A: In the Resource Usage view timescale, type hours to adjust the resource's assignments.

Answer B: Display the Resource Allocation view. Select the assignment you want to delay. In the Leveling Delay field, type the length of delay that you want to add to the task in elapsed days.

Answer C: In the Resource Usage view, select the resource assignment you want to delay. In the Task Form, display the Resource Schedule table and type the delay you want to add in the Leveling Delay field.

Answer D: In the Resource Usage view, select the resource assignment you want to delay. In the Task Form, display the Resource Schedule table and type the delay you want to add in the Assignment Delay field.

No peeking! Scroll below the book ordering information to read the answer to this quiz. 


Order the the MCTS Self-Paced Training Kit (Exam 70-632): Managing Projects with Microsoft Office Project 2007.

To learn more about Microsoft certification, read, "Microsoft Project Management Certification: How to Get Started."

Read Microsoft's exam topics list for 70-632 here.

Author Bonnie Biafore


Bonnie Biafore is the author of O'Reilly's Microsoft Project 2010: The Missing Manual and Microsoft Press' On Time! On Track! On Target! Managing Your Projects Successfully with Microsoft Project. She's developing a Project 2010 course for lynda.com. As a consultant, she manages projects for clients and wins accolades for her ability to herd cats. You can learn more at Bonnie's website or email her at bonnie.biafore@gmail.com. 


The Answer to Test Yourself!

Answers B, C, and D are all correct. The Resource Allocation view displays the Resource Usage view in the top pane and the Leveling Gantt in the bottom pane. The table in the Leveling Gantt view contains the Leveling Delay column, so you can type the length of delay that you want to add to the task.
You can also add delays in the Task Form. Right-click the Task Form and display the Resource Schedule table. Type a delay for an entire task in the Leveling Delay field. To delay an assignment, type the value in the Delay field.

Answer A is incorrect. You can change work hours in the Resource Usage view timescale. However, these changes introduce date constraints to the task and you must manually adjust the work hours if your schedule changes.

 