Certification Insider: Resourcing Project Plans 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Share the Love! MPUG Community Leader Awards
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
How to Get Certified in Microsoft Project 2010
Microsoft Project 2010 Certification FAQ
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
 
 

Got a project to complete? Better get some resources or the work won't get done. You can add resources to your Project file or -- for resources you share between projects -- a resource pool. If you use Project Server, you create enterprise resources on your Project Server. When you finally assign resources to tasks, Project calculates the project schedule and cost. Work and material resources have been around for ages, but cost resources are new to Microsoft Project 2007. Because the Project certification exams have questions about new features, you had better understand the difference between work, material, and cost resources as well as when to use each type.

You might think that Project's work resource type is for labor resources, that is, people. But time is what differentiates work resources from other types. A work resource is anyone or anything you track by the amount of time it contributes -- a carpenter hammering nails for 20 days or a backhoe used to dig a trench for eight hours.

Work resources affect both schedule and cost. How much time work resources have available and when they're available directly affects how long their assigned tasks take (see my October 2008 column, "Certification Insider: How Calendars Control Schedules"). Work resources typically come with a time-based rate, for example, equipment you rent by the hour, a contractor paid by the month, or an employee who earns an annual salary. These time-based rates multiplied by the time resources work on a task determine the price tag for work resource assignments.

 Cost based on anything other than time is the telltale characteristic of a material resource: $1 for a commemorative margarita glass, $3 for one bag of fresh limes, and $30 for one liter of tequila -- for the project close-out party, of course. The cost rate field for a material resource represents the cost per unit. The unit of measurement (glass, bushel, or gallon in the party example) is for your reference so you enter the correct cost per unit. Project calculates the cost for an assigned material resource by multiplying the cost per unit by the quantity you assign. The only way materials can affect a schedule is if their delivery task is delayed.

Cost resources, the new entrant in Project 2007 resourcing, are pure cost. No time. No other quantities but money. For that reason, cost resources are perfect for costs not associated with people, equipment, or materials, for example, airfare, meals, registration fees, and training class costs.

In Project 2003 and earlier versions, you had to use the Fixed Cost field to add costs like these to tasks, which meant that you had to keep track of different categories of costs outside of Project. In Project 2007, a task can have a separate cost resource for each type of cost so you can track how much you spend on each, as shown in Figure 1.

Figure 1: In Project 2007 a task can have a separate cost resource for each type of cost.

Biafore Figure 1

Work and material resources have fields to identify the resource rates. Here are the cost fields you define for work and material resources and what they do:

  • Std. Rate (Standard rate) applies to both work and material resources. For a work resource, this field represents the cost per time period. For example, a contractor's pay rate of $50 per hour shows up as $50.00/hr. Project automatically adds “/hr” to the number you type. If the work resource cost is based on a different time unit, type it after the dollar amount, for instance, $5000/mon. For Material resources, Std. Rate represents the price per unit, where the unit is whatever you type in the Material Label field. For example, for tequila, the Material Label unit might be liter. When you type $30 in the Std. Rate field, Project calculates cost as $30 per liter.
  • Ovt. Rate (Overtime rate) applies only to Work resources. It's the rate charged if a resource works longer than the standard work day. Salaried workers typically don't earn overtime, so their Ovt. Rate is zero. If someone gets the same hourly rate regardless how many hours they work, the Std. Rate and Ovt. Rate fields are equal. For anyone who earns a premium for overtime, type that value in the Ovt. Rate cell.

Note: Project doesn't automatically use the overtime rate when resources are over-allocated (that is, assigned to work longer than the standard work day. You must designate overtime hours in a resource assignment to tell Project to apply the overtime rate, which you'll learn in a future column.

  • Cost/Use refers to an amount you pay each time you use a resource, such as a flat $50 each time a support person travels to your office. Each time you assign that support person to a task, the task cost includes the hourly rate for the person and $50 for their appearance.
  • Accrue At is important if you have to track when money is spent, for example, paid up front, after the work is done, or spread out over time. Setting “Accrue at” to Start means the cost occurs when the task begins -- like paying for a product before the vendor ships it to you. End represents cost paid at the end of a task, such as paying a contractor only when the work is complete and you approve it. Prorated spreads the cost over the duration of the task, such as the wages you pay to employees assigned to long tasks.

The Cost resource type is nothing but cost, so you don't have to fill in any kind of cost fields in the Resource Sheet. You specify the cost when you assign the Cost resource to a task. That way, the cost can vary between tasks. If a task requires a trip from Boston to New York, you could assign the Airfare cost resource to the task with a cost of $199. For a task with a trip from Boston to Melbourne, Australia, you might assign the Airfare cost resource with a cost of $1150.

Think You Know Resources? Test Yourself!

You must estimate the total cost of a project to put on a conference in Minneapolis. Team members must make several trips to the conference site. Your company sets a person's travel cost limit to $150 per day for lodging and $50 per day for food, unless a manager approves a higher cost. You use $400 as a guideline for a single domestic airfare.

What cost fields must you define to track the costs for a two-person, two-day site evaluation task?

A: Create three Cost resources for airfare, lodging, and meals. Fill in the Airfare resource's Cost field with $400, the Lodging resource's Cost field with $150 and the Meal resource's Cost field with $50.

B: Assign the Airfare, Lodging, and Meals Cost resources to the site evaluation task. Fill in the Cost field for the Airfare assignment with $800, the Lodging Cost field with $600, and the Meal Cost field with $200.

C: Assign the Airfare, Lodging, and Meals Cost resources to the site evaluation task. Fill in the Cost field for the Airfare assignment with $400, the Lodging Cost field with $300, and the Meal Cost field with $100.

D: Assign the Airfare, Lodging, and Meals Cost resources to the site evaluation task. Fill in the Cost field for the Airfare assignment with $1600, the Lodging Cost field with $600, and the Meal Cost field with $200.

No peeking! Scroll below the book ordering information to read the answer to this quiz.


Order the the MCTS Self-Paced Training Kit (Exam 70-632): Managing Projects with Microsoft Office Project 2007.

To learn more about Microsoft certification, read, "Microsoft Project Management Certification: How to Get Started."

Read Microsoft's exam topics list for 70-632 here.

Author Bonnie Biafore


Bonnie Biafore is a PMP (that’s Project Management Professional, not pimp). She is the author of
Project 2007: The Missing Manual and On Time! On Track! On Target! (a book about project management not Project) along with about a dozen other books. You can learn more at her Web site http://www.bonniebiafore.com or email Bonnie at bonnie.biafore (at) gmail.com. Read her project management blog, Scope Creep & Other Project Management Monsters, at http://www.oreillynet.com/mmprojectmanagement/blog/.

 


The Answer to Test Yourself!

B is correct. A cost resource represents a pure cost incurred by a task, so you assign the cost to the task, not the cost resource. You can apply more than one cost resource to a task. The value you fill in is the total cost for that Cost resource for the task. In this example, the task requires two airfares of $400, for a total of $800. The task has two people on site for two days, so the Lodging cost is $150 multiplied by two days and two people for a total of $600. Meals are for two people for two days for a total of $200.

A is incorrect. You set the cost for a cost resource by typing the value in the Cost field of a task's Cost resource assignment, not by assigning a cost in the Resource Sheet.

C is incorrect. The value is the total cost for a Cost resource for that task, not the basic cost for a single person for a single day. In this example, two people travel, so the total airfare is for two flights, and thus $800.

Answer option D is incorrect. Because each person incurs a single airfare, the Airfare cost is $800, not $1600. 