How Gantt Chart-Literate Are You: The Puzzler Solution 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Share the Love! MPUG Community Leader Awards
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
How to Get Certified in Microsoft Project 2010
Microsoft Project 2010 Certification FAQ
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
 
 

In my last article, "How Gantt Chart-Literate Are You?," I posed a challenge to you. Only one person noticed that if an entire portfolio is scheduled to start on April fool’s day, it can't be taken too seriously. However, here is my solution (seriously!).

Here's the original chart:

The Gantt Chart Puzzler

Project AAAA: Started late by almost one week, is up-to-date, and is forecasted to take two business days longer than its original duration (20d). Action item for the portfolio manager:

  1. Explore ways to shorten the project duration to bring forecasted finish date back to the baseline finish date.

Project BBBB: Started early by a few days and is not up-to-date. The early forecasted finish date isn't reliable, but is forecasted currently to take one day longer (21d instead of 20d). Action items for the portfolio manager:

  1. Ask project manager BBBB the clarifying question: have you updated your schedule as per the start of the 16th of this month, or have you left remaining work scheduled in the past?
  2. Urge the project manager BBBB to update the schedule (correctly).
  3. Review the  up-to-date schedule.

Project CCCC: Started late by a few days and is not up-to-date. The on-time forecast finish isn't reliable, but the duration is currently forecasted to take two fewer days (18d instead of 20d). Action items for the portfolio manager:

  1. Ask project manager CCCC the clarifying question: Have you updated your schedule as per the start of the 16th of this month, or have you left remaining work scheduled in the past?
  2. Urge the project manager CCCC to update his or her schedule (correctly).
  3. Review the up-to-date schedule.

After scrutinizing the responses, I've concluded that only three people had a perfect analysis and strong recommendations:

  • Jim Peters
  • Joe Slade
  • Cliff Barbour

Since Jim was the first one in with the best response, he wins the book. But I definitely give an honorable nod to Joe and Cliff. Thanks to all of you who entered!

Author Eric Uyttewaal
Eric Uyttewaal, PMP, is the president and CEO of ProjectPro Corp., which specializes in consulting and training related to Microsoft Project, Project Server, and Portfolio Server. Eric is the author of the upcoming book, Forecast Scheduling with Microsoft Project 2009. Formerly, he was Executive Director, Microsoft EPM Division, at the International Institute for Learning (IIL) in New York. At IIL he developed and managed the White, Orange, Blue, and Black Belt certification curriculum in Microsoft Project and Project Server. He has been involved in projects ranging from a few thousand dollars to $150 million. Reach him at ericu (at) projectProcorp.com or call the company at (613) 692-7778.
 