How to Achieve a More Realistic Schedule in Your Project Planning 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
True Leaders! MPUG Community Leader Awards
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
 
 

Project management has moved front and center in organizations as an antidote to heightened competitiveness, greater appetite for innovation, and ever-shrinking budgets and resources. The project management profession is rapidly evolving, bringing in new methodologies, tools, and utilities to do the best job possible. Yet, quite often project managers still lack some key techniques for achieving better project planning and scheduling. In this article, I share some tools and methods that can aid PMs in improving the quality of their planning and in achieving a more realistic project plan that they feel confident of committing to.

The Nature of the Scheduling Challenge

Statistics show that between 60 and 70 percent of projects don't meet their schedule, budget, or predefined scope. Why is this?

In many companies the process of planning a project consists of compiling a predefined list of tasks with logical connections and duration estimates in a deterministic or constant quantity. Some companies do this plus also add in information about resource assignments. Still others use enterprise project management applications as a timing engine with no resource constraints.

An additional means of honing a schedule is to analyze various scenarios, performing resource leveling to discover conflicts and critical chains, and mapping critical paths that could cause the entire project to deviate from its planned finish date.

Another challenge that directly affects the quality of planning is the experience level of the project manager in charge of maintaining the schedule. Frequently, these newbies have no planning experience, no management experience, and no project management experience. All of a sudden they're expected to deal for the first time with building a project plan, assigning resources, creating a budget, and managing the scope.

Is it any wonder that so many projects start off underfunded or under-scheduled from their very first day?

In all of these cases, scheduling is a critical ingredient during the first stages of a project, no more so than in companies where pricing of projects is done according to a project's Gantt chart with some added predefined cost buffer. There must be a better way to achieve a more realistic schedule and map critical paths/chains.

Pre-measuring a One-time Event

A project is a concentrated effort done once to achieve a product or a service. If it's unique (done once), how can the effort it will require be measured accurately?

By using known tools, you can "release" the constraint of uniqueness and of those deterministic durations that don't reflect the "real world." What it takes is the application of simple Monte-Carlo techniques. Running each project numerous times using simulation wears away the uniqueness constraint. Each simulation represents a different scenario or a different mix of durations for the same project plan. Each time a new random duration is produced for each task -- based on the task's distribution/curve and the predefined deviation range -- a new project plan or scenario is created.

What's a task's distribution? Time for a quick stats lesson. A task distribution is a random occurrence that can be defined as an asymmetric right-tailed beta curve/distribution. (The use of a triangular distribution is a common way to simplify statistical problems in project management.) What's that right-tail curve with an asymptote at y=0 represent? The project or task may never end, but with a minor probability. That means the minimal expected duration of a task will always have a positive value. It's common to assume 80 percent success for a given task's duration, meaning that if that task were done 10 times, then eight out of 10 times it would meet its deadline or finish before it.

Figure 1: A task's duration according to beta and triangular distribution.

Katz Figure 1
For each scenario we need to concoct for our Monte Carlo simulation, relevant data is collected and stored as for the project's finish date/remaining duration, the critical path/chain, and the critical resources. The exit point for each batch we run is the definition of estimated task deviations. This can be one range for all tasks, such as 30 percent above and 10 percent below, or it can be defined task by task.

Here are some key points to keep in mind as you're building a simulation utility in your project plan.

  • Say you're going to use a defined task deviation of 30 percent probability that the project will be late and a 10 percent probability of it being early. That sets a task with an estimate of 10 days to an upper bound or delay of 13 days and a lower bound or early delivery of nine days. The deviated data can be entered into the project's pert fields by task or can be set as a generic deviation to all tasks. The former configuration combined with a random function to randomly set task durations between the pre-configured deviations would create a large range of different scenarios for a single project.
  • Work with "remaining work." Bolster your analysis in both the planning stage and the execution stage by using the durations of tasks that haven't begun and the remaining durations of tasks that have begun. Exploit what you already know.
  • Use the built-in leveling algorithm in Project to differentiate between critical path and critical chains. Confused about the difference? A critical path is the longest path of tasks that starts at a project’s start date and ends at a project’s finish date; as I mentioned, any delay on a task in this path will cause the entire project to deviate from its planned finish date. The emphasis is on the task order. A critical chain is just like a critical path in regards to resource constraints. But in a critical chain if two tasks share the same resource and are in parallel to one another, they'll shift in priority according to the predefined resource leveling settings. The emphasis is on the resource.
  • Display the results of the calculated finish dates and durations in a descending order (Pareto) to see the percentile for each total duration/finish date and the number of times it occurred in the simulation run.

Once you have the simulation run, what's next? The outputs are the result of a wide range of scenarios where each scenario has tasks with both optimistic durations and pessimistic durations. These have been randomly generated according to the predefined distribution function. These task deviations can cause planned serial connected tasks to become parallel and vice versa.

For example, let's say a project's deterministic duration is 18 months. That's what your initial plan calls for (deterministic durations). Yet the simulation utility shows that in 85 percent of the cases (from all of the checked scenarios), the project actually finishes in 24 months. This insight should raise a red flag. If this project is priced predicated on being finished in 18 months, both the client and the contractor would lose -- the contractor because he or she had resources planned for 18 months, yet there's a high probability they'll still be working on the project for another six months, and the customer because not getting the project done on time may affect the viability of the effort as well as his or her reputation in the organization.

Map Hidden Paths or Chains

The hidden critical chains or paths in a project is an array of feasible paths that connect a project from its beginning to its end, yet in their deterministic state they don't hold the longest path. A hidden critical path or chain can become the critical path or chain if one of its tasks deviates -- takes more time than planned -- causing that hidden path or chain to become the longest path from start to end.

How do you counter this possibility? Go through the simulation process keeping in mind the project's critical path or chain for each iteration. Due to a different scenario generated (tasks take longer or shorter than their original duration) different paths and chains show up.

For example, a critical path in the deterministic project might be based on tasks 1, 2, 5, 7, and 9. Yet the output from the simulation runs might show that 70 percent of the time the path might follow 1, 2, 3, 7, 8, and 9. How would that affect the schedule?

Improve the Quality of the Project Plan

The project plan is the base for all project progress and status. A well-built project plan is a key factor for estimating the project's progress and overall success. The closer the project plan is to reality, the more successful it's likely to be. So how can you improve a project's plan?

An obvious solution is to reuse historical knowledge that can supply immediate feedback to a project's manager during all stages of the initiative regarding its progress and its chances of finishing on time, in scope, and on budget.

I suggest adding as part of a company's project management process a list of automated checks. The checklist can be run manually. Or, if you have the capabilities, you can automate it. This involves running through business rules. An initial set of rules can be marked as critical. Saving or publishing of project plans can be blocked if a critical rule doesn't pass.

I'd advise dividing the project's checklist into three parts: project level checks, resource level checks, and task level checks. The checklist can be used in all stages of a project (initiation, progress, and so on) as can be seen in the following predefined checklist:

  • The total slack for this task is negative.
  • There is no work planned for...
  • The task is critical and was scheduled to be finished by now.
  • The task has no predecessors.
  • According to ______ the task's progress it is going to miss its planned schedule.
  • The task should have started but is 0% completed.
  • The task is scheduled to start in the future yet it is partially complete.
  • The task is not a summary task nor is it a milestone, yet there are no resources assigned to it.
  • The task is partially complete, yet not all of its predecessors are done.

This checklist is an infrastructure element that can be modified, added to, or deleted from, enabling companies to force their own business rules or just relay best practices.

Continuous Improvement is the Goal

In this article I've pointed out a few of the more common challenges regarding project plans; yet these are only a small portion of the daily problems project managers and companies face every day. I've also offered some techniques for improving a project plan. With just a small effort, you can achieve great added value from analyzing what you already know in different ways as part of your on-going process for continuous improvement.

Aric Katz