How to Restore an Abandoned Project Schedule 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
True Leaders! MPUG Community Leader Awards
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
 
 

Ever known someone with a once-beautiful old car that’s been left to rust away -- their once prized possession now forgotten in the weeds? Often, a project manager's schedules succumb to a similar fate.

Consider what would happen if you were to tow that car out of the weeds and take on the project of restoring it. Once restored, it would be very valuable, indeed -- a vehicle you'd be proud to own and drive. Reworking and restoring a project schedule, the vehicle that moves the project along, can be similarly rewarding.

In this article I share basic steps for picking up an abandoned project and restoring it.

Examine the Logic of the Project

First, you'll want to take an inventory of what you have. Open your schedule and really look at it. Far too often, owners of schedules treat them like spreadsheets, never expanding the view over to the right to include the Gantt view. They're caught up in the numbers and dates, failing to look at the logical flow and relationships. Try rolling the sections up to highest level and begin to expand each level. Does it make sense? More often than not, what I frequently see at this point are more lines going up and down than left to right, in some cases almost completely covering up the Gantt bars (as shown in Figure 1).

Figure 1. An example of the "bar code" project schedule.

Watson Figure 1

This is what I like to call a "bar code." I even had one client who tried to scan it thinking perhaps some higher power was at play sending a message of pending doom or that there was some hidden master plot to sabotage the project.

This generally crops up with schedule owners who know just enough to be dangerous. They've heard that constraints can be bad; so in an attempt to avoid these, they manipulate the links tying everything back to anchor dates (usually the start) while abusing lead and lag in order to force the dates where they think they should be. It has been said that nearly 75 percent of all links in most schedules are redundant in nature.

If your schedule looks like this, it’s time to strip the whole thing down to each individual part, just like when you restore an antique car. Remove the rust, moss, and weeds by deleting many of the relationships. Now it’s time to reexamine each part. Do the hours, durations, and resources make sense? Do these need to be revised? More often than not, they do. Time is your friend here. Think about what you’ve learned from the onset of the project. Now is the time to start applying some of that hindsight.

Peel Back Resource Assignments

Over-allocation is another area to scrutinize. This can potentially be even worse if you're working in an enterprise environment. Switch to the resource usage view and change the time scale to weeks or months. Look for the weeks or months that show up in red. Many people get too carried away here trying to solve at too granular a level. If you see one week with 60 hours followed by one with 20 hours, for example, its best to assume some averaging will occur. Resources will work according to their schedule rather than some mandate your schedule has assigned to them. They’re likely smarter than we give them credit for.

Most people get themselves into trouble from the very start by using the default, out of the box task type (Fixed Units). When you assign by this method, everything is assigned at 100 percent. Before long, you have a resource assigned more than a thousand hours in a month. Given that the average work month is around 160 hours, how do you imagine the work will get done? Short of being able to instantly clone people, it’s not going to work.

Here’s something else to consider. Who works on only one task at a time, 100 percent of the time? I don’t know anyone who does, so why assign work that way? A better way is to use fixed duration, non-effort driven. You can always change it after the schedule is complete. Most people can estimate how many hours something will take. Keep in mind; your resources more than likely have other things they'll be doing already, so give them more time (duration) to get work accomplished. Let Project do its job and calculate units. If you did a good job, you should see something, I'd hope, less than 75 percent units at most. This amounts to about 30 hours a week which, with everything else on someone’s plate, is a reasonable number provided they have no other major assignments at the same time. In summary, always book your resources to less than 100 percent units.

Last Step: Reassembly

After you've cleaned up each task, begin reassembling the pieces starting with the highest level first and working your way down to the lowest level. Last but not least, be sure to reschedule your unfinished work and update your schedule to current status date.

Figure 2. The same project's summary outline, after restoration.

Watson Figure 2

Reworking your project schedule by completing these steps will reward you with a beautifully restored vehicle you can proudly drive around the organization.

Kevin Watson
With over 25 years of project management experience, Kevin Watson, PMP, MCT, MCTS, is a black belt in Microsoft Project and Microsoft Project Server. Kevin brings a unique combination of project management and project server to the field, where he is a Senior Consultant with Microsoft. Contact him at