5 Principles of Program Management for the London Olympics 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Share the Love! MPUG Community Leader Awards
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
How to Get Certified in Microsoft Project 2010
Microsoft Project 2010 Certification FAQ
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
 
 

Ky Nichol heads up the major sporting events practice for global consultancy Pcubed. That has included work for both the 2004 Summer Olympic and Paralympic Games in Athens and the 2006 FIFA World Cup hosted in Germany. Most recently, he's been involved with the 2012 Summer Olympic and Paralympic Games. The latter are scheduled to take place in London from July 27 to August 12, 2012.

Aerial view of the Olympic Stadium
Aerial view of the Olympic Stadium. Image courtesy of London 2012

Nichol, who has been in project management for two decades, honed his expertise through working on major initiatives for NASA, the European Space Agency, and Accenture, as well as organizations in the high tech manufacturing and transport sectors.

Nichol and his Pcubed team work with Games organizations to oversee program and risk management, perform assurance, and advise on senior stakeholder reporting. Tools used include applications from both Microsoft and Primavera Systems (now part of Oracle). The Microsoft products in use include SharePoint, Project Professional 2007, and Enterprise Project Management (EPM) Solution.

5 Principles of Big Events

Nichol adheres to five key principles in his work on Olympic Games, culled from his experience in delivering large, multi-agency initiatives:

1. Integrate the organizing bodies early on.
2. Keep the end state in mind from the start.
3. Avoid early independence of projects.
4. Engender an appetite for organizational change.
5. Baseline early.

1. Integrate the Organizing Bodies Early On

"In the heyday of a bid, you put a bid book together, and you've got to sell it to many committees" says Nichol. "It's all positive and [describes] lots of spend."

The bid book lays out who is going to deliver what in order to make the Olympics happen. The players -- primarily, the Organizing Committee and the Delivery Authority -- need to agree about who's actually responsible for what piece of the plan. Setting that out clearly and early is essential, says Nichol. Any ambiguity later in the project can generate disagreements. "Early agreement and clarity will save a lot of time and effort down the line. In our work with the 2006 FIFA World Cup in Germany they had integration at the top of their agenda and it worked to great effect," he points out.

   View of the Velodrome. Image courtesy of London 2012
The outside of the Velodrome2. Keep the End State in Mind from the Start

"London has developed a great pitch for what these big structures are going to do after the games," explains Nichol. He can recount war stories about previous Olympics where facilities ended up in disarray post-event.

For London, legacy came first in the planning, says Nichol. For example, the main stadium requires 80,000 seats; but few continually operating stadiums need that much capacity. So London will build a stadium with 25,000 permanent seats. The other 55,000 will be temporary. Once the Games end, those temporary seats will be sold, and the remaining stadium will be ready for more traditional sporting event use.

Legacy planning also faces challenges. Currently, with the economic downturn, it's hard to get private developers interested in developing venues, such as the Olympics Villages, which will be sold as housing apartments after the Games end. "There are venues such as Villages that typically rely on private sector funding and in the current climate there's less capital for them to obtain the financing they need," says Nichol.

 

3. Avoid Early Independence of Projects

When the program teams are just starting their work, says Nichol, there's a tendency to send each one off to tackle development of a particular venue. That approach can lead to scope gaps. Interface areas usually suffer -- for example the scope boundary between the venues and the connecting projects such as roads and common domain.

He encourages the various entities involved in the whole project to keep the program teams together as if they were part of one single team until a detailed and apportioned master plan is available. Without that integration, filling the scope gaps that surface downstream will have to come out of somebody's contingency budget, "and you'll end up applying for additional funding, which is not a popular move," he says.

To help avoid issues like this, the teams held a number of scope reviews to identify the gaps. "Sometimes, there's double-accounting," says Nichol, "which is good because you can make savings."


The Challenge of Reporting

Nichol considers management reporting a good indicator of whether things are in control or not. "Can [participants] put clearly on one page what the program is going to deliver together with accurate status data? ”Nichol asks. "If they can't do that, then something's broken somewhere -- no matter what the excuse is."

Nichol and his team have helped Games organizations put in place effective reporting solutions from dashboard reporting that helped Athens work with the IOC to assisting London 2012’s Olympic Delivery Authority in reporting status to Funding parties.

To help organizations put together fact based reporting for senior stakeholder, Pcubed has developed a proprietary system, the Pcubed Delivery Hub. As Nichol explains, the Hub draws from multiple scheduling engines and other systems to produce standard dashboards that allow users to drill down on the details from a high level.


4. Inspire an Appetite for Organizational Change

"The people you start up these things with aren't necessarily the people you need downstream," Nichol says. "There's got to be some clever human resources strategy in this."

The Games are, ultimately, a temporary job that requires specific kinds of expertise. Those in charge of hiring want to attract the right kind of talent from around the world to do the work required, which may only last a couple of years. That may require premium pay -- more than you'd like to pay, says Nichol -- "because you're only going to get them for two years, and they're taking some risk."

Also, although there's a body of people who tend to move from Olympics to Olympics, says Nichol, there are also a lot of government workers from the host city government involved. These people will go back to other jobs once the Games are over.

Keeping these two kinds of people engaged and working well together requires effective stakeholder management and team building, Nichol says. On the Athens Olympic Games this encompassed "some well planned team building and great management together with some really good parties" to bring people together.

5. Baseline Early

"You've got to have some measuring point that people are working toward," says Nichol. Without it, the team will go into disarray and "you'll lose time hand over fist." When deadlines start to slide, says Nichol, there's no spending more money nor changing the deadline. "Unfortunately in this case all you can do is scale the scope back."

   BMX track during the Games. Image courtesy of London 2012
BMX track during the Games.For example, he says, early, during the process of setting up a Bid Book, many venues will be "iconic. Every venue will have a signature architect." But as work moves ahead, reality sets in. There isn't budget to fulfill the ambitious plans, and organizers are forced to take temporary measures "with things overlaid on to make them look good for the Games." Those iconic facilities often end up being more traditional, less expensive structures.

Yet, that's also the reality of putting on a major event like the Olympics. Setting milestones is a constant challenge in planning the Games. First, the vision for the Olympics has to developed way before the actual work required can be laid out and priced in detail. In the case of the London Games, the initial bid submission was mid-July 2003. London was selected as the final location two years later, in July 2005. As one instance of the volatility of the entire process, two sports -- baseball and softball -- that were part of London's bid were dropped by the IOC two days after London was chosen as the host city. At the same time, the IOC pondered whether to add other sports as replacements. How do you properly plan for venues that you may not need or may not even know about?

Second, there are multiple levels of reporting involved. First, there are the C-level milestones, which need to be reported to the International Olympic Committee. Those involve the major pieces of the entire project. Then there are internal high-level milestones that get reported up into the UK government. Those get broken into sub-programs, projects, and workstreams, which lay out what the individual workers will be doing on any given day.

Nichol has put in over three years toward the London Olympics effort to date -- "in and out for pieces," he points out. Will he have a front row seat to the spectacle? Perhaps, but that isn't something the master planner has actually planned for yet. But, as he explains, "I’ll be early in line for tickets and hope I get some."