Task Types: Don't Get Frustrated! 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
Project Portfolio Management: Align Project Resources with Business Strategy
Team Players: Exchanging Project Data with Your Development Team
Ask the Experts: A Successful EPM Implementation Has More than Technology
Dealing With Uncertainty in Project Schedules
Microsoft Project Options you want to know about
Performance Tuning Your Scheduling Practices
Project Options You Want to Know About
Microsoft Community Leader Award Winners
8 Important Lessons I Learned During EPM Implementations
Insights for Scheduling
Creating an Agile Schedule with MS Project
Ask the Experts: Similar Task Names
Habits: Why Trader Joe’s Serves Free Coffee Every Day of the Year
Toolbar and Menu Commands for Microsoft Project 2007
 
 

When people stumble in their use of Microsoft Project, frequently the problem stems from a lack of understanding of how task types work. If you understand that, then Project can become the most powerful weapon in your project management arsenal. In this article I explain the basics of task types.

For each task in your project, you must set three task type choices:

  • Fixed Units (Project's default)
  • Fixed Work
  • Fixed Duration

To understand these, you have to learn the underlying formula used by the scheduling engine:

Duration * Units = Work

Before I explain each aspect of the formula, please note that with this formula, as you change any given component, that will change the other components too. For any tasks, you can choose which piece of the equation Project will calculate by setting the task type.

Duration is the length of a task measured in business or calendar day.

Units is the number of resources assigned to work on a task. For example, if a person is available 10 hours per week (assuming a standard 40-hour week), this represents a quarter of her available time. The Units equal 25 percent.

I should note that in my experience, resources are rarely available a hundred percent of the time unless they work on only a single project.

Work is the amount of effort a resource must expend on a task, usually measured in units such as hours per week. The total work for a task is the sum of all those time units, no matter how many resources are assigned to the task.

Regarding work, there are some tasks that you can add more resources to and the task's duration will decrease. This is called effort-driven scheduling, which is Project's default. The duration of a task will shrink or grow as resources are added or removed, while the amount of total effort expended on that task stays the same.

For example if you have a week long task to test several units, you can decrease the amount of duration by adding more testers. For other tasks, adding resources won't decrease the duration, such as training. No matter how many instructors one assigns to a three-day training course, it will still take three days. Another example is backing up a computer. One person or 10 can back up a computer -- it will still take the same amount of time. Effort-driven scheduling only occurs if you keep this option clicked in the Task Information dialog and you add or remove resources from a task. (Keep in mind that when you add resources to a task, this does cause some increase to the task's duration due to increased communication needs between the resources.)

Here are the steps for selecting a task type for one or more tasks in Project 2007:

  1. Open your project plan and select the task or tasks you desire to change. If choosing multiple tasks, you can click and drag for serial tasks or click and Ctrl-click to select non-serial tasks.
  2. Select the Task Information button and go to the Advanced tab. If you only select one task, you can double-click anywhere on the task row to open the Task Information dialog box.

Figure 1. The Task Information button

Reinheimer Figure 1

Use the Task type: drop-down menu to select the appropriate task type. Select the Effort Driven checkbox if desired. Note! Most of the time I leave "Effort-driven" unchecked.

Reinheimer Figure 2

As I stated earlier, you must set your task to be one of three types. So how do you know which one to use? Here are some guidelines.

Fixed Units Tasks

Fixed unit tasks means that in the formula Duration * Units = Work the units are fixed. Use Fixed Unit tasks in situations such as:

  • When the number of resources you have for the task is the first or main thing you know.
  • When you can't get more resources to do the work -- your resources are fixed.
  • When you want to change the duration or the work on a task while keeping the number of people working on the task the same (assignment units).
  • When you want to keep the resource working on a task at a certain percentage of his or her available hours.

Here are a few tips about this type of task:

  • This type usually isn't used as much as fixed work and fixed duration.
  • Fixed unit is Project's default.
  • Note! I rarely used fixed units. I mainly use fixed work and fixed duration.

Fixed Work Tasks

Fixed work tasks means that in the formula Duration * Units = Work the work is fixed. Use Fixed Work tasks in situations such as:

  • When the effort required is the first thing you estimate.
  • When the effort required is the easiest thing to estimate. Estimating effort is usually easier and more accurate than estimating duration.
  • When your resources give you task estimates in work hours. For example, developers and engineers typically give work estimates in hours.

Fixed Duration Tasks

Fixed duration tasks means that in the formula Duration * Units = Work the duration is fixed. Use Fixed Duration tasks in situations such as:

  • When the duration is the first thing you estimate.
  • If the duration stays the same when adding resources, such as training or backing up a computer system.
  • Tasks that always have a group of resources assigned, such as meetings or training.
  • When the deadline is so tight that it's the primary driver for the duration of the task. You have to make it work within the available timeframe. This situation has been prevalent in most of the organizations I've worked with.
  • When the workload isn't your problem, such as when external resources are consultants.

There are two simple guidelines to remember when determining task types. If you remember these guidelines, you'll be able to predict how Microsoft Project will respond as you enter duration, units, and/or work.

Guideline #1: Enter the duration estimate or work estimate and fix that number by setting the Task Type accordingly. Fixing it prevents Project from changing it.

If you enter a Duration estimate, set the Task Type to Fixed Duration.

If you enter a Work estimate, set the Task Type to Fixed Work.

Guideline #2: Provide the second value in the formula Duration * Units = Work and let Project calculate the third value. If you created a fixed duration task, assign the resources you need and let Project calculate the work. If you created a fixed work task, assign the resources and let duration be calculated. If you entered the duration and work, Project only needs to know who will do the task and it will calculate the number of resources needed (units).

Note! Always provide only two of the three values in the formula.

Here's a chart you can print and stick next to your laptop until it becomes second nature to you:

Field that you change Field calculated if the task is Fixed Duration Field calculated if the task is Fixed Units Field calculated if the task is Fixed Work
 Work  Units are recalculated  Duration is recalculated  Duration is recalculated
 Duration  Work is recalculated  Work is recalculated  Units are recalculated
 Units  Work is recalculated  Duration is recalculated  Duration is recalculated

As a general rule the priority of which variable will most likely change is duration, then work, and then units.

If you can master the concept of task types, you'll be well on your way to fully understanding how Project works and how to use its capabilities to your best advantage -- and your frustrations will diminish.

John Reinheimer, PMP, PMI-SP, MCP, has been using Project for 18-plus years. He has worked as a scheduler, project manager, trainer, and PMO developer at several companies, including DirecTV, Mattel, Boeing, Blue Cross Blue Shield of Florida, and Fidelity Information Services. John is an independent consultant currently working with the United States Navy on a $1.7 billion unmanned vehicle program. Contact him at johnnyrein@earthlink.net.