The All-Time, Number-One Mistake Made by Schedulers 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
Project Portfolio Management: Align Project Resources with Business Strategy
Team Players: Exchanging Project Data with Your Development Team
Ask the Experts: A Successful EPM Implementation Has More than Technology
Dealing With Uncertainty in Project Schedules
Microsoft Project Options you want to know about
Performance Tuning Your Scheduling Practices
Project Options You Want to Know About
Microsoft Community Leader Award Winners
8 Important Lessons I Learned During EPM Implementations
Insights for Scheduling
Creating an Agile Schedule with MS Project
Ask the Experts: Similar Task Names
Habits: Why Trader Joe’s Serves Free Coffee Every Day of the Year
Toolbar and Menu Commands for Microsoft Project 2007
 
 

The following is an excerpt from Eric Uyttewaal's new book, Forecast Scheduling with Microsoft Project 2010.

Forecast Scheduling book cover

 

The "Schedule"

Most people understand the schedule as a list of deliverables and their due dates. To a professional scheduler that list of deliverables and their due dates is not the schedule, but the baseline schedule. The baseline schedule is a frozen copy of the approved schedule. It's the target you work towards and compare progress against.

Many users of Microsoft Project don't realize that the approved version of the schedule can be copied to and isolated as the baseline schedule. Others don't realize that there's a feature in Microsoft Project that allows you to do this very easily. All these people treat the schedule itself as a collection of promised dates that need to stay the same, which is really the role of the baseline schedule. These people become reluctant to make any changes to the schedule once it has been approved. They stop using the schedule as a dynamic model to explore the impact of changes and suggest ideas for solutions. This is similar to being the doctor of a dead patient; there's no need to monitor or intervene any longer.


Win a Copy of Eric Uyttewaal's New Book!

Eric is giving away a copy of his new book, Forecast Scheduling with Microsoft Project 2010, to two lucky MPUG readers. To enter the drawing, answer this question: What's the price of Eric's new book before the early-order discount? (Your clue: Check out the purchase link he includes below.) Email your answer before midnight on December 10, 2010 to editor@mpug.com. Use the subject header "Book."


Instead, project managers need to treat the schedule as a living body to be constantly updated with the latest available data. Now, the doctor has a live patient and will need a thermometer to measure the temperature of the patient. The doctor will also need a standard of reference to determine if the temperature is normal (37.5 degrees Celsius or 98.6 degrees Fahrenheit). Better yet, the doctor needs a range with control limits for the body temperature to determine if corrective action should be undertaken. For project managers:

  • The project itself is the live body of the patient.
  • The dynamic model of the project is the thermometer.
  • The baseline schedule (or the set of deadlines) is the standard of reference.
  • The organization (including the project management office, portfolio managers, and executives) should specify the control limits.

The dynamic model and the baseline schedule together will tell you how much the project is behind or ahead.

The "Baseline Schedule"

We hope you recognize that the baseline feature in Microsoft Project is a major feature -- very beneficial and very important. It allows you to actually monitor and control your living project. Alternatively, you should have at least a set of deadlines to work towards.

In the illustration below you can see that each task bar is split into two parts when setting the baseline. The top part (with the gray shade) is the current schedule -- the dynamic model of the project. The bottom part (solid black) is the static baseline -- the target schedule. The baseline schedule is an important artifact that should be handled with care; the baseline is essentially the contract between you as the project manager and the external customer or between you and the internal sponsor of the project. The baseline should remain the same throughout the project unless there's a valid reason to change it. Like every contract, it requires careful change control, as explained in PMI's Practice Standard for Project Configuration Management, published in 2007.

Uyttewaal Figure 1

Questions to Consider

So, how did we get into this situation where many users of scheduling applications are treating the schedule itself as the target instead of treating it as a dynamic model? Why does just about every single executive mandate that the schedule can't and shouldn't change? What happens is that Project users treat the schedule as cast in concrete? Are they wrong? Or are we professional schedulers wrong?

Who should make the adjustment here? There are two ways forward...

Should the user of Microsoft Project learn about baseline schedules and how to create them? Should they educate their executives that it's the baseline schedule that won't change, whereas the live schedule (dynamic model) is supposed to change to keep it reflecting the project and to have a tool with which what-if scenarios can be explored?

Or...

Should the professional scheduler forget about the term "baseline schedule" and start treating the word "schedule" like everybody else in this world is treating it today--as the list of deliverables and their due dates? Should we then replace the term "schedule" as we know it today with another term, such as "project model"? This term clearly communicates that what we create is something alive -- something that should not be kept static and killed. Should we stop referring to ourselves as "schedulers" and start calling ourselves "project modelers"? A scheduler clearly doesn't create a schedule; a scheduler receives a schedule (a list of deliverables and their due dates) and then creates a model of the project that will help the project team meet its schedule--their contract.

At the last PMI-College of Scheduling Organization (COS) conference in Calgary in May 2010, we even considered the term "Project Prophet" for the entire length of a hundredth of a second. Then we laughed about this joke (compliments of Primavera's Joel Koppelman).

As professionals, we have arrived at a crossing here, and we'll have to make up our minds sooner rather than later. Will you start calling yourself Project Modeler?

If you're interested in chiming in on discussions like this and on other "scheduling" issues, please join our public LinkedIn group, "Forecast Scheduling."

Eric UyttewaalPre-order the book before Dec 11, 2010 for a 50% discount at http://www.projectprocorp.com/products.php.
Eric Uyttewaal, PMP, MCITP, MVP, is the president and CEO of
ProjectPro Corp., which specializes in consulting and training related to Microsoft Project, Project Server, and Portfolio Server. Eric is the author of the book, Forecast Scheduling with Microsoft Project 2010. Formerly, he was Executive Director, Microsoft EPM Division, at the International Institute for Learning (IIL) in New York. At IIL he developed and managed the White, Orange, Blue, and Black Belt certification curriculum in Microsoft Project and Project Server. He has been involved in projects ranging from a few thousand dollars to $150 million. Reach him at EricU (at) ProjectProCorp.com or call the company at (613) 692-7778.