Skip to main content
Go Search
MPUG Home
Membership
Resources
User Group Chapters
Knowledge Library
About MPUG
MySite
  

 

The Purpose of Project Charters 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Share the Love! MPUG Community Leader Awards
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
How to Get Certified in Microsoft Project 2010
Microsoft Project 2010 Certification FAQ
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
 
 

The Project Success Method book coverHow often have you been involved in a project where the customer and the project team didn't seem to share the same understanding of the project definition? Frequently, what the project manager sees as newly revealed requirements tend to be viewed by the customer as requirements that should have been obvious from the beginning. In this article, which is a brief excerpt from The Project Success Method, a Wiley book, author Clinton M. Padgett explains the first task of a new project team: development of a written charter that clearly defines project scope and other key project requirements...

Bonus! Listen to a 15-minute MPUG podcast featuring author Clinton Padgett here. Just choose to save the MP3 file to your hard drive and tune in with Windows Media Player. Padgett explains why so many projects fail, shares the steps for the project success method, lays out why he believes time is more important than cost or quality, provides a technique for establishing a project's critical path, and offers a method for implementing the practices described in the book.

The first and most obvious purpose of a project charter is that it ensures that all the project stakeholders formally agree on the project definition and have recorded that definition in writing. The charter protects the project team against uncontrolled scope creep and the other disasters awaiting project teams that begin their work with only a vague or assumed understanding of the project scope and other requirements.

As a project manager, you want to involve all project stakeholders directly in creating the project charter. Ideally, the customer will participate directly in developing the project charter. Whether the customer participates directly or not, you as a project manager are well advised to ask the customer and all other project stakeholders to sign the charter to show their personal acceptance and commitment to the project definition.

In other words, if the customer won't participate with the team in defining the project, then the team should define the project and put the responsibility on the customer to either accept their definition or revise it. If the customer decides later to expand project scope or modify other requirements, then the project team and the customer must go through a formal charter revision process, during which all project requirements and constraints are open to discussion, renegotiation, and possible modification.

Project managers and teams in the construction industry learned the importance of this lesson centuries ago. The signed agreement between the customer and the contractor clearly defines project scope based on plans and specifications. If the customer asks for an additional feature, the contractor and customer must negotiate the added fee for the increase in project scope as well as other revisions to the agreement, such as changes to the project's scheduled completion date. In effect, a “change order” on a construction project is a revision to the project charter.

In other types of projects, however, project teams too often fail to follow this prudent discipline. This failure is especially common when the project customer is within the same organization as the project team. Keep in mind that any conversation about project scope and other requirements—no matter how comprehensive and concise it may seem to you—is no substitute for a written document that is signed by the stakeholders.

Another advantage of involving the project customer in the chartering process is that it usually gets the project started earlier and gives the team the maximum amount of time to get the project done. I have seen many cases where everyone in an organization knows that there is a major project to be done, and maybe they have a year to get it done. But senior management consumes the first six months procrastinating and dithering on specifying the project scope and other requirements. The chartering process forces the customer to grapple with the issues associated with the project definition and to make the necessary decisions, so that the project team can get started with its work.

The project charter has two other important purposes, as well. First, the process of developing the charter is as important as the document itself. The charter development process is an excellent opportunity—coming as it does at the earliest stage of a project—to involve the new team in teamwork, which leads to the development of a real team as I described in Chapter 4. And because of their direct involvement in the chartering process, the team members begin to take ownership of the project; that is, they begin to think of the project as our project, rather than as someone else's project that I would like to have as little involvement in as possible. So the chartering process helps to build a real team and to build commitment to the project.

There's often a strong temptation to have one person draft the charter for review by all stakeholders. However, this “straw-man” approach short-circuits the teamwork and commitment-building value of the chartering process. A far better approach is to have the stakeholders start with a nearly blank sheet of paper and develop the charter together. This approach virtually always leads to a better charter. All stakeholders are actively involved and their views are represented. The process highlights contentious issues and enables stakeholders to tackle and resolve them at the most advantageous time in the process; that is, at the very beginning.

Second, the project charter serves as an efficient and consistent means of communicating the project definition to people who were not involved in the charter development deliberations, such as people who join the project team later, contractors and other resources who will work on the project, or managers of the functional departments from which the team members are drawn.

Because the project charter is such an important communications device, you should ensure that it:

  • Is concise. My basic rule is that the charter should never exceed three pages, plus attachments, and would ideally be two pages or less.
  • Avoids using technical jargon and undefined acronyms that may not be understood by some readers.
  • Is written as a management document rather than a technical specifications document.

Reprinted by permission of the publisher, John Wiley & Sons, Inc., from The Project Success Method: A Proven Approach for Achieving Superior Project Performance in as Little as 5 Days, by Clinton M. Padgett. Copyright (c) 2009 by Clinton M. Padgett.

To order a copy of The Project Success Method, visit Wiley or your favorite bookseller.

Clinton M. Padgett
Clinton M. Padgett is President and CEO of Project Success, Inc. (PSI), a consultancy focused on helping clients develop excellence in project management. For over 15 years, he has provided consulting and training to clients in a wide range of industries. Contact him at Clint.Padgett@projectsuccess.com.

 