Using the Portfolio Dashboard to Uncover the Value of Projects 

News Archive
Ask the Teacher: Earned Value Doesn’t Want to Calculate
Setting Recurring Non-working Time in Microsoft Office Project Standard 2007
Back to the Future
Ask the Teacher: Substituting Resources, Plus Changing the Current Date
4 Formulas for EPM Disaster
Ask the Experts: Define Critical
Oracle on Track to Buy Primavera
Ask the Experts: Why Self-Taught with Microsoft Project Isn't Such a Great Idea
Laying the Foundation for Leading a Project Management Office
Mail: Another Perspective on Defining "Critical"
Certification Insider: Creating a Project from an Existing One
A Rational Approach to Padding
Ask the Expert: Accounting for Material Resources
Chapter Spotlight: 3 Questions with London's Dharmesh Patel
Olympian Stephanie Trafton Connects Winning the Gold with Project Management
5 Compelling Reasons to Upgrade to Project 2007: Visual Reports
Ask the Experts: Displaying Availability Exceptions in Resource Usage Sheet
Certification Insider: How Calendars Control Schedules
Chapter Spotlight: 4 Questions with Houston's Vicki Eaker
The 30-second Report
Ask the Expert: Separating Time Completed from Work Completed
Certification Insider: Defining Working Times with Project 2007 Calendars
Columns I'd Like to See in Project
PMI Releases Updates to Four Standards
How to Reduce Your Project Costs
Ask the Expert: Custom Reports in Microsoft Project
The Work Breakdown Structure
The Strategies of Microsoft Project and Project Server
Certification Insider: Ready! Set! Start Creating Tasks!
Track Project Progress with Physical % Complete
Putting Project Portfolio Management to Work in a Bad Economy
Chapter Spotlight: 4 Questions with Twin Cities' Larry Christofaro
11 Reasons You Should Attend the Microsoft Project Conference
The Case of the Broken Task in Microsoft Project
Ask the Expert: Importing Data from Excel into Project
Certification Insider: Arranging Tasks
Ask the Expert: When Scheduling, Start at the Beginning
Chapter Spotlight: 3 Questions with Baltimore-Washington Metro's Gerald Leonard
Ask the Expert: Tips for Getting Project Server Buy-in from Users
Migrating to Microsoft Project Server 2007: Lessons from the Field
How Gantt Chart-Literate Are You?
Develop Your Project Management Skills: Scenes in the Negotiation Play
Ask the Expert: Optimize Microsoft Project Performance
Ask the Expert: Creating a Limited Resource Availability Schedule
Scheduling Master: Finish to Start Successors
How Gantt Chart-Literate Are You: The Puzzler Solution
The Power of Local Resources in Microsoft Project Server
Certification Insider: How To Influence Tasks and Win Friends (in Microsoft Project)
Ask the Experts: When % Complete Won't Calculate
Ask the Experts: Making Interim Plans Work for You
Project Budgeting: Money Changes Everything
Ask the Experts: How Resource Sharing Works in a Master Project
5 Principles of Program Management for the London Olympics
Certification Insider: Resourcing Project Plans
How to Replace Generic Resources with Named Resources
Ask the Experts: Building What-if Slack Time into Your Schedule
Automated Governance for Portfolio Management
Earn Your PMI-SP, Part 1: Explore the Credential
Creating Microsoft Project Custom Toolbars in 4 Steps
Certification Insider: Assigning Resources in Microsoft Project
Ask the Experts: When Linking Summary Tasks Makes Sense
Earn Your PMI-SP, Part 2: The Application Process and Getting Through the Exam
Working the Numbers: How to Inject Financial Savvy into Project Management
MPUG Thanks Community Leaders in Award Ceremony
Tips and Tricks for Microsoft Project 2007: Creating Useful Custom Views
Ask the Experts: Applying Two Constraints on One Task
Earn Your PMI-SP, Part 3: What You Need to Study
Best Practices for Microsoft Project, Part 1
Best Practices for Microsoft Project, Part 2
Certification Insider: Mastering Duration, Work, and Units
Creating Milestone Reports in Microsoft Project
Ask the Experts: Managing That Schedule with Drop-dead Deadlines
The Project 2010 Interview: Microsoft's Chris Capossela Talks to the Microsoft Project Community
How to Restore an Abandoned Project Schedule
Certification Insider: Modifying Resource Assignments
Why MPUG: Five Perspectives, One Member
The Purpose of Project Charters
Forecasting Schedule Issues with a Deadline Dashboard
Ask the Experts: Printing Notes in a Project
How to Achieve a More Realistic Schedule in Your Project Planning
Is Microsoft Project a Project Management Tool?
The New Year's Resolution of a Project Manager
Certification Insider: Understand Critical Path
Project Programming: Integrating Project Server's Timesheet with an Access Control System
Ask the Experts: What's Going on This Week?
Critical Path 2.0
Certification Insider: Exchanging Data between Programs
ProjecTalk Goes On the Air!
Ask the Experts: Making Sense of Current Activity Reports
Three Rules for a Happy Life with Project 2007
Project Date Numbering
Sign Up for MPUG Chapter Alerts!
MPUG Members: Tell Us What You're Going to Love about Microsoft Project 2010 -- and Get a Free Copy of the Software!
Microsoft Project 2010: Preparing for Launch
Certification Insider: Saving and Modifying Baselines
Ask the Experts: Creating a Report with Task and Resource Data
Microsoft Project 2010 Licensing
Microsoft Project 2010 Upgrade Path
Project Server 2010: Things to Note, and Avoid, as You Start the 2010 Journey
5 Tips for Formatting Text on a Gantt Chart
Microsoft Project 2010 Feature Rally: Sync to SharePoint
Microsoft Project 2010 Feature Rally: Manually Scheduled Tasks
Microsoft Project 2010 Feature Rally: Departmental Fields
Microsoft Project 2010 Feature Rally: Inactive Tasks
Microsoft Project 2010 Feature Rally: Team Planner
Microsoft Project 2010 Feature Rally: Reporting
Microsoft Project 2010 Feature Rally: The Ribbon
Microsoft Project 2010 Feature Rally: Synching with SharePoint
Microsoft Project 2010 Feature Rally: Project Timeline
Microsoft Project 2010 Feature Rally: Integrated Portfolio Management
Microsoft Project 2010 Feature Rally: No More ActiveX!
Microsoft Project 2010 Feature Rally: ROG, the Red Over-allocation Guy
Certification Insider: Making Resource Assignments Realistic
Ask the Experts: Exporting Only Tasks to Excel
The Great Demo! Top 10 List
The Great Demo! Top 10 List
Microsoft Project View Mastery
EPK Cost Tackles Cost Management for Microsoft Project Server
Lock Down Microsoft Project Progress Data
Certification Insider: Resource Overallocations
Don't Touch That Dial! What to Do Before Using Microsoft Project
Ask the Experts: Managing a Large Number of Resources
10 Easy Ways to Earn PDUs
The Awful Demo: Top 10 List of What NOT to Do
Microsoft Project Certification 2010 - How To Guide
Microsoft Project Certification 2010 Frequently Asked Questions
Ask the Experts: Quick Project Status Report
Schedule Tasks Your Way
Start Your Project Management Career
Calendar Exceptions in Microsoft Project 2010
Social Networking in Project Management, Part 1: Using Twitter
Ask the Experts: Updating the Baseline
Keeping Your Project Schedules Updated by the Team without Microsoft Project
Social Networking in Project Management, Part 2: Using Facebook, Blogging, and More
PMI Keynoters Clinton and Kundra Highly Value PMers
Laser Construction Wins PMI's Project of the Year Award
MPUG Mega-Guide for Learning Project 2010
Ask the Experts: Reports on Over-allocated Resources
Get To Your Control Documents Easily!
Three Reporting Questions
Certification Insider: Tracking Project Progress
The All-Time, Number-One Mistake Made by Schedulers
5 Reasons Not to Attend a PMP Exam Boot Camp
Ask the Experts: Bothersome Behavior of the New Version of My Old Friend
A Microsoft Project Beta Exam Experience
Certification Insider: Managing Multiple Projects
Focus: Getting Your Project People on the Same Page
A Call to Action: What is a Project "Schedule"?
Focus on Analytics: Stopping Project Derailments
Task Types: Don't Get Frustrated!
Ask the Experts: Configuring the Project Server 2010 Enterprise Global Template
Response to "What is a Project Schedule?"
Focusing on Deliverables, Not Just the Schedule
Certification Insider: Microsoft Project Budgets and Costs
Ask the Experts: Is Microsoft Project Overkill? And the Task Inspector Equivalent
The Basics of Estimation with Microsoft Project
How to Sell Project Management to Senior Executives Who Don't Want It
The Model Project Management Office
The Project Communication Plan
A Master at Project Management
Ask the Experts: Working Offline in Project Server 2010
10 Trends Ruling Project Management That Will Affect Your Future
Chapter Spotlight: 4 Questions with Madison's Wendy Anderson
How to Get Certified in Microsoft Project 2010
Certification Insider: Project Reporting
10 Key Business Analysis Trends to Guide Your IT Organization to Greater Results in 2011
Ask the Experts: 15 Microsoft Project Tips for New Users
Creating a High Performance Project Team
Tips for Taking the Microsoft Project 2010 Certification Exam
The Missing Link in Microsoft Project 2010: Project Financial Intelligence
Arpan Shah, Head of Microsoft Project Product Management, Discusses Service Pack 1
The Seven Deadly Sins of Project Schedules
Ask the Experts: Hammock Tasks
Project Management Advice: The Price of Right
Certification Insider: Analyzing Variance with Microsoft Project
How To Display Lag between Tasks in Your Gantt Chart
Tips on Handling a Problem Team Member on your Project
The Art and Science of Estimating Task Lengths
High-flying Jumpstart: Cloud-based Project Management
How to Use Free Analyst Reports to Build Your Case for Microsoft Project
Ask the Experts: Combining Resources across Projects
When Did You Revise the Estimates?
What's the Status of the Program? Dynamic Program Reporting
When Are You Working? Updating a Resource Calendar
Cost Decisions in Project Management Accounting
Ask the Experts: The Case of the Calendar Changes
Project Directions: Microsoft's Arpan Shah Fields Questions
What You Need to Know about Project Server 2010 Service Pack 1, Part 1
pmi2011
Is Project Management a Profession?
Project Pearls: Eliminate Over-Allocations
Microsoft Project on the Go
Ask the Experts: Selling your Message with the Project 2010 Timeline View
Quick Access Toolbar for Easy Navigation in Microsoft Project
Using Project Management for Social Change
Change Management during a Project Server Implementation
The Most-Read MPUG Microsoft Project Articles of 2011
The Most Viewed MPUG Forums Threads of 2011
Three Common Principles for Project Initiation
Ask the Experts: Over-allocation with 2.5 Hours of Work?
Group Resources for Effective Reports!
Too Tired to Care? Regain Your Perspective with 5 Proven Practices
Ask the Experts: Tying Tasks and Assignments across Projects
Manage Scheduling Contingency
Project Portfolio Management: Align Project Resources with Business Strategy
Team Players: Exchanging Project Data with Your Development Team
Ask the Experts: A Successful EPM Implementation Has More than Technology
Dealing With Uncertainty in Project Schedules
Microsoft Project Options you want to know about
Performance Tuning Your Scheduling Practices
Project Options You Want to Know About
Microsoft Community Leader Award Winners
8 Important Lessons I Learned During EPM Implementations
Insights for Scheduling
Creating an Agile Schedule with MS Project
Ask the Experts: Similar Task Names
Habits: Why Trader Joe’s Serves Free Coffee Every Day of the Year
Toolbar and Menu Commands for Microsoft Project 2007
 
 

When your executives are wondering which projects are delivering the biggest bang for their investments, the tool you can turn to for delivering the data is Microsoft Office Project Portfolio Server 2007. A major component of Microsoft Office Enterprise Project Management (EPM), Portfolio Server integrates with Office Project Server 2007 to deliver visibility across projects in a consolidated manner. In a previous article I discussed the Builder and Optimizer modules for Microsoft Office Project Portfolio Server 2007. This article addresses the third module, the Portfolio Dashboard.

Portfolio Server 2007 allows you to define and automate four governance phases: Create, Select, Plan, and Manage. The Manage phase involves updating "optimized" projects with actual cost and schedule data and tracking progress using the Portfolio Dashboard.

The Dashboard module provides a customizable "scorecard" view of portfolio health. You enter tracking data and status reports into the Builder module, and it can be reviewed by stakeholders and portfolio managers in the Dashboard module.

To access the Portfolio Dashboard, click on the Dashboard circled in red shown in Figure 1.

The Portfolio Dashboard is similar to the My Scorecard view except the Dashboard illustrates project status. As can be seen in Figure 1, the 10 variables encompassed in the example are:

  • Overall
  • Financial
  • Resource
  • Schedule
  • Risk
  • Scope
  • IT Budget 2007
  • Bus Budget 2007
  • Ops Budget 2007
  • Benefits

Associated with each are green, yellow and red graphical indicators that provide status information about the projects.

Figure 1. The red circle shows you where to open the Dashboard.

Vesey Figure 1

The green, yellow and red graphical indicators can be configured by the system administrator based on the criteria determined by management. Figure 2 shows examples of the green, yellow, and red graphical indicator criteria. While many of the graphical indicators are based on statistical calculations, the Overall Status indicator is keyed in manually each month by the project manager.

Figure 2. Examples of graphical indicators on the Dashboard.

Vesey Figure 2

Figure 1 shows that the Focus Group Product Implementation project has red indicators for Overall Status, Financial and Schedule; yellow indicators for Resource and Risk; and green indicators for Scope. The red and yellow graphical indicators show that this project isn't going well, and management may question whether to continue investing in it.

Clicking on the project takes the user to the Project Information tab shown in Figure 3. It's advisable to select the relevant tabs in order to investigate why the graphical indicators are red or yellow for the particular project. While the Project Information and other tabs provide valuable information about the project, it's important to view the Status tab in order to see explanations of the red and yellow graphical indicators. To access the Status tab, click on the diamond in the upper right corner indicated with a blue arrow and then select Status indicated with a red arrow.

Figure 3. The Project Information tab allows you to drill down on a project.

Vesey Figure 3

Figure 4 shows the Status tab for the Focus Group Product Implementation project. As I mentioned above, the Overall Health Description (circled in red) was keyed in by the project manager and provides information on the cause for the red indicator.

Figure 4. Snapshot Reports show the status indicators for each aspect of a given project.

Vesey Figure 4

It's also possible to review the status of the other variables by simply clicking on the appropriate indicator. For example, the Financial Actual next to Overall Status is also red, based on the formula shown in Figure 2. By clicking on the Financial Actual indicator, Figure 5 appears with an Indicator comment provided by the project manager explaining why Financial Actual is red.

Figure 5. Indicator comments allow you as project manager to explain the causes for a given status.

Vesey Figure 5

The Thresholds button in Figure 4 shows examples of the green, yellow and red graphical indicator criteria indicated in Figure 2 above.

Figure 6 shows monthly Snapshot Reports of the project status from January through May, 2006. As I mentioned in a previous article, "Managing Reports with Microsoft Office Project Portfolio Server 2007," Snapshot Reports are available on the Project Status, Cost Tracking and Resource Tracking Tabs. The purpose of the Snapshot Reports is to be able to compare on a monthly basis the project status, cost tracking or resource tracking progress for a project.

Figure 6. The Snapshot Report for a project over a five-month period. 

Vesey Figure 6

To create, delete, or lock Snapshot Reports open the Project Status tab and click the New Snapshot or Delete Snapshot circled in red in the upper right corner. Lock prevents a Snapshot Report from being edited.

When creating a new Snapshot Report, keep the default names or rename the Archive Report or the New Report as shown in Figure 7.

Figure 7. Once you've named a new Snapshot Report, you can open it in View instead of Edit.

Vesey Figure 7

Once the Snapshot Report has been created, open the project in View instead of Edit, go the Status Tab and use the pull down menu shown in Figure 6 to see previous Snapshot Reports.


Author Bill VeseyBill Vesey, PMP and MPA member of the Baltimore-Washington D.C. Metro Chapter, is the head of Project Management Services. He has over 20 years of enterprise project management (EPM), project management, and program management experience. His expertise includes establishing Project and Program Management Offices (PMO), conducting OPM3 and Capability Maturity Model (CMM) organizational maturity assessments, writing project management policies and procedures, configuring Microsoft EPM 2003 software to support project management policies and procedures, developing portfolio management procedures that align projects with strategic plans, and mentoring and training project managers, team members, executives, and resource managers. Contact Bill at wvesey@verizon.net