What I would really like to see is a report that would show me all tasks that are due by week. When I use the date range filter, I am getting too many tasks. How could I create this report?

I like this question because it is something many users would like and have been looking for. There is a little used option in grouping called intervals that could help you with this request. Here’s how to use it:

Create a group called “Tasks by Week”

  1. Project | Group by | More Groups | New.
  2. Name: Tasks by Week, Group by: Finish, Select a color | Define Group Intervals.
  3. In the Define Group Interval form: Group on | Weeks, Group Interval 1 for every week.
  4. Click OK to close the Define Interval form. Click OK to close and save the Group Definition.
  5. To test: Click on the Task by Week Group | Click Apply.

Another option: If you would like the tasks grouped by week by resource, add Resource Name as a secondary grouping next to “Then by”

Tasks by Week Report

Below is an example of the result. You can expand and contract each week to show the detail. Using the Show button on the formatting toolbar and selecting level 1 will expand and contact all the groups at once. This grouping may now be applied to any task report or view.

Tasks by Week Report

Using Define Group Interval opens up many options and possibilities for creative reporting. Define Interval isn’t available for all fields in the database. Try date field or a number field (such as duration, priority, % complete, cost, etc.) as well as custom fields including text fields among others. Resource grouping is also available.

Note: The group you created exists in the one project that it was created in. To allow the grouping to be available in other project schedules, copy the object through the organizer: Tools | Organizer | Groups | select the object on the right and copy it to the left.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Tasks by Week Report

What I would really like to see is a report that would show me all tasks that are due by week. When I use the date range filter, I am […]

2 min read
•over 18 years ago•Updated 9 months ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Context Engineering for Project Managers: Give AI the Project, Not Just the Question
Articles
1 min read

Context Engineering for Project Managers: Give AI the Project, Not Just the Question

Learn how to choose, date, and source the project information you give AI, so its risk analyses, status reports, and change request reviews reflect your actual project.

A
Anonymous
4 days ago
Read
The Climbing Rope – Why Projects Rise or Fall Together
Articles
1 min read

The Climbing Rope – Why Projects Rise or Fall Together

Ronald B. Smith uses a climbing rope to show how project team dynamics like trust, communication, and shared accountability decide who reaches the summit.

A
Anonymous
17 days ago
Read
Asana AI Teammates Are Now Included in Paid Tiers — and Billed by Consumption After That
Articles
1 min read

Asana AI Teammates Are Now Included in Paid Tiers — and Billed by Consumption After That

MPUG Editorial · September 18, 2026 · ~4 min read · Category: PM Platforms From mid-September, Asana AI Teammates and the Dash assistant are included in the company’s paid Agentic […]

A
Anonymous
25 days ago
Read
Explore All Articles