Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Cost resources are a very useful feature of Project (and also therefore of Project Server), but there is at least one rule you need to follow.   Rather than telling you how to use cost resources, please read the following Microsoft excerpt to see why costs and resources really don’t mix on the same task.

Using Cost Resources: Best Practice

So, now you know what cost resources are, and you are probably thinking that they are really neat, and in truth, they are.

Do not mix cost and work resources on the same task

However, please be aware that when assigning a cost resource to a task, best practise dictates that cost resources should not be mixed with any other resources assigned to the task (note this is exactly what Microsoft’s blog article does do!)  This is because, if a cost and work resource are assigned to the task, and progress is used to track the task (ie marking it 100% complete), then Project will update progress for the work resource and not for the cost resource.  This is because Microsoft did not want you to inadvertently accrue the cost of the cost resource when progressing the task.

If you only have cost resources assigned to a task, then progressing the task (ie marking it 100% complete), will accrue the cost for the cost resource(s) assigned to the task.

Obviously the above can (and does cause confusion), hence this best practise blog – I’ll walk you through this.   I’ve set up 3 cost resources with different accrual types (because that’s the way they would generally work in real life, you pay airfares upfront, hotels when you leave, and meals as you go along), and a single work resource.  In the 1st instance, I’ve assigned them as Microsoft’s blog suggests, assigning cost and work resources to the same task (note in the screen shot below I’m viewing two windows in Project, showing you the resource sheet (at the bottom) and a split view showing the Gantt Chart and the Task form (with costs) (at the top).

 Using Cost Resources: Best Practice

When I update the Task using the % complete field, only the WORK RESOURCE (ie Ben) is affected.

 Using Cost Resources: Best Practice

In order to update the costs on the Cost Resources, I need to manually edit the Actual Cost field in the form.

 Using Cost Resources: Best Practice

So, this is perhaps a little too obscure for the majority of users, so to implement this as per the best practise would require splitting the Visit Customer into two tasks.

Best Practise – place the cost resources on a separate task

This is the same project as the one above, but this time I’ve split out the cost resources onto a separate task (and inserted the cost fields into the table).

 Using Cost Resources: Best Practice

Let’s set the status date to Friday the 11th Jan, and status the project (and as usual with my projects, everything is on track!).

I’m expecting to have spend £500 on the airfare (accrued at the start of the task), £100 on meals (prorata), and £0 on the hotel (I’ve not yet checked out).

I can quickly use the Update Project button to status the whole project, this is my preferred method and then I amend the things that haven’t gone to plan.

Using Cost Resources: Best Practice

The project now looks like this.

 Using Cost Resources: Best Practice

So, this way, by separating the work resources and cost resources onto separate tasks, everything works as you would expect.

Kudos must go to Adrian Jenkins of Microsoft for the explanation of how this works – thanks Adrian, and to fellow Project MVP Nenad Trajkovski who brought it to my attention.

Enjoy,  Ben.

For more blog posts by Ben, visit applepark.co.uk

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Using Cost Resources: Best Practice

Cost resources are a very useful feature of Project (and also therefore of Project Server), but there is at least one rule you need to follow.   Rather than telling […]

3 min read
•over 13 years ago•Updated 7 months ago•
B
Ben HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
B
Ben Howard

Content Writer

Ben Howard – Awarded Community Leader for his very popular and comprehensive UK web training series and has over 30 years of experience of implementing enterprise solutions for customers worldwide.  During that time, he’s worked for IBM, DELL, and Microsoft, as well as several smaller organisations. He now runs his own consultancy (Applepark Ltd), providing Project, Project Online and Power BI implementation and training services. He has been awarded the Microsoft Most Value Professional award for Project for the last 13 years, blogs semi-frequently at www.applepark.co.uk, produces video training for Pluralsight and his own YouTube channel, and finally was responsible for producing P2O, an application that exports tasks from Microsoft Project into Outlook.  You can catch him at ben@applepark.co.uk  

View all articles by Ben Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

monday.com AI Workflows Now Pause for Human Approval
Articles
1 min read

monday.com AI Workflows Now Pause for Human Approval

MPUG Editorial · August 26, 2026 · ~4 min read · Category: PM Platforms monday.com AI Workflows can now stop mid-run and wait for a person to say yes. The […]

A
Anonymous
about 12 hours ago
Read
Ask Gemini in Google Chat: An AI Command Line Aimed Squarely at Status Chasing
Articles
1 min read

Ask Gemini in Google Chat: An AI Command Line Aimed Squarely at Status Chasing

MPUG Editorial · August 25, 2026 · ~5 min read · Category: Productivity Tech Starting August 26, 2026, Ask Gemini in Google Chat puts a single prompt box inside the place most […]

A
Anonymous
1 day ago
Read
Copilot Meeting Prep Lands in Classic Outlook for Windows
Articles
1 min read

Copilot Meeting Prep Lands in Classic Outlook for Windows

MPUG Editorial · August 24, 2026 · ~4 min read · Category: AI & Copilot Copilot meeting prep — the feature that assembles context, action items, and documents before a […]

A
Anonymous
2 days ago
Read
Explore All Articles