Allocation of multiple resources to one task

Home Forums Discussion Forum Allocation of multiple resources to one task

Viewing 1 reply thread
  • Author
    Posts
    • #297496
      Matt Matulewicz
      Guest

      I assigned two resources at differing % to one task of 142 hours. Will be working to break it down under 80 later.
      The problem I have is at the end of the task, one of the resources shows no allocation for a period of 5 weeks.
      Why won’t MS Project 2010 evenly allocate the resources to the task evenly?

    • #300797
      Sai Prasad
      Participant

      Matt – Since you have hinted one of the resource has no allocation for a period of 5 weeks, check if there are exceptions (holidays) set for this resource. What is the Task type and Effort driven? It would be good if you can provide a screenshot of this assignment?

Viewing 1 reply thread
  • You must be logged in to reply to this topic.