Application of Islamic weekend

Home Forums Discussion Forum Application of Islamic weekend

Viewing 2 reply threads
  • Author
    Posts
    • #400717
      Stergios Kokkoris
      Guest

      Dear friends,

      I set, according to Islamic calendar the Friday as non working day for the whole schedule, but I want to do a couple of Fridays.
      How can I do that?
      Thank you in advance for your help.

      kind regards

      Stergios Kokkoris

    • #400718
      Stergios Kokkoris
      Guest

      Sorry,

      I resend my inquiry. It sent incomplete by accident.

      Dear friends,

      I set, according to Islamic calendar the Friday as non working day for the whole schedule, but I want to set a couple of Fridays as working days.
      How can I do that?
      Thank you in advance for your help.

      kind regards

      Stergios Kokkoris

    • #400737
      Julie Sheets
      Guest

      As odd as it sounds, you’d create an exception to make the occassional Friday a working day. Assuming you have altered the calendar to make all Fridays non-working, open the calendar and select the Friday you’d like to work. Click the Exceptions tab in the Change Working Time dialog. Give the exception a name, click in the start or finish field to the right. Click the Details button. Click the Working times option and enter the working times for that day. Repeat as needed for other days.

      • #401042
        Stergios Kokkoris
        Guest

        Thank you very much Julie, I appreciate your help

Viewing 2 reply threads
  • You must be logged in to reply to this topic.