How to show % Complete of a particular task in EPM Project Center view

Home Forums Discussion Forum How to show % Complete of a particular task in EPM Project Center view

Viewing 0 reply threads
  • Author
    Posts
    • #198900
      Calvin Zhang
      Participant

      In EPM project center, there is an existing “% Complete” column showing an overall project completion status. If I would like to show a “% complete of a particular subtask” for every project, how to set it up in Server Settings? I am using MS Project 2010.

Viewing 0 reply threads
  • You must be logged in to reply to this topic.