    Hello, I’m trying to create a single report similar to the Project Overview that would report on multiple, similar projects at once.

    For example I am leading the renovation of multiple apartments. I would have a project file for each of the apartments. We are moving resources in stages and some are deployed simultaneously.

    I’d like to run a single report that shows all of the upcoming activity, any late activity and the project status.

    When I create a master report of a project file that has each apartment in as a subproject it gives me a summary in bar chart form of the completion status of each apartment but doesnt give me any milestones, upcoming or late tasks.

    Is there anyway to do this from a single report? Thanks in advance!

    #408964 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Community Leader
    • Expert
    • Forum Pro

    Jerry, it’s been a while since the last time I worked with master projects but here’s a suggestion. Create a temporary master project by inserting the sub-projects without linking them (when you insert the project (deselect the Link to project checkbox). This will create a single project and allow you to report across all of them. You can either create the reports in a blank project or copy the report to your global to be able to reuse. Someone might have a more “formal, accurate, best practice” answer but this will at least get you the combined report you are asking.

    #409099 Reply

    Jerry Todd

    Hi, what needed to happen was to expand the tasks by clicking the arrow next to it – then they all could be seen as part of the reports. Thanks for your help