Printing a Tracking Gantt View (Project 2010)

Home Forums Discussion Forum Printing a Tracking Gantt View (Project 2010)

Viewing 2 reply threads
  • Author
    Posts
    • #219502
      Michael DeMarie
      Participant

      It seems that when printing from Project 2010 the Tracking Gantt view does not print, rather the Gantt chart prints without the baseline bars. Is it possible to print (actually plot to a large-format plotter) the Gantt chart with the baseline bars?

    • #220652
      J Fox
      Guest

      Did you look at Format/Format/Bar Styles? it’s different for each view.

    • #220701
      Michael DeMarie
      Participant

      J Fox – You are a genius! I used the Gantt Chart Wizard while in the Tracking Gantt view, added the baseline bars and all prints perfectly.

      Thanks!