Home › Forums › Discussion Forum › Project Online OData Schema
Tagged: OData Schema
Is there a picture of the OData schema somewhere to easily see how the tables are related?
Thanks
John
I have looked high and low for such a thing, but nothing turned up.
In my experience it’s a bit of trial-and-error. You could try creating a pivot table that pulls in all tables. It’s kludgy (and whatever you do, don’t refresh lest you break the network) but it should give you a high level view.
As for a list of possible GUID relationships, that also eludes me. But I’ve gotten by fine so far using any fields that have “ID” in the name.
Hope this helps!
Christopher,
Thanks for response and recommendation on how to create a quasi schema.
I will try it …
Thanks
John