For MS Project 2013, I created a grouping template which groups all tasks/stories by workstream within a sprint. There are many stories owned by each workstream within a sprint and each story has a number as it was created in Github. How can I modify the grouping view, so that with each sprint, there is a group by workstream and then within each workstream, the stories are numbered in ascending order?
Amy, you should be able to add a sort by story. Group by sprint and then workstream, and sort by story. You can’t create a sort entry like you can with grouping, but the sort persists and you can re-sort on demand pretty easily. Hope that helps…?