Show Physical % Complete on Your Task Bars

To illustrate how much of a task is done when you’re working with Microsoft Project, just insert a PHYSICAL % COMPLETE line to the Bar Styles dialog box as shown below. Note that Project doesn’t draw a PHYSICAL % COMPLETE bar if the Actual Start is NA.

Ismet Kocaman physical complete

 

 

Written by Ismet Kocaman
Ismet Kocaman, MCTS, PMP, is a Mechanical Engineer and has more than 15 years of project management experience in the manufacturing sector. He currently provides consultancy to small to mid-sized companies on project management, reorganizing, and streamlining the manufacturing operations. He also conducts training seminars for engineers on MS Project. Contact Ismet at ikocaman.pm@gmail.com.
Share This Post
Have your say!
00
1 Comment
  1. I have a similar question relating to bar styles, instead of the physical percent field, I am using a number field to obtain progress. How do I show that in the progress bar?

Leave a Reply