Milestones:-Do We Need to Assign a Resource to Them in Microsoft Project?

There is a lot of discussion surrounding the question of resources being assigned to milestones using Microsoft Project. The answer to this question is (Isn’t it always?), “It depends.” The milestone is the checkpoint. Its main characteristic is that it has no duration (duration for a “classic” milestone is 0 (days, weeks, hours…). The best practice is that you should start a set of tasks with a summary task (to group them), and end the set of tasks with a milestone. Here is a simple example:

As you can see, there are some tasks for writing the article, and they finish with the milestone which I called “Article done.” The duration for the milestone is 0 days. Each task, except the milestone, has an assigned resource. Now, before I start explaining when and why you should or shouldn’t have a resource assigned to a milestone, let’s take a look at what happens if I mark all tasks, except the milestone, 100% complete.

As you can see if the milestone is not marked as completed, and all other tasks are, the summary task (in my case, the whole project) will only show as 99% finished. So, the milestone is 1%!

As you know, when a resource is assigned to a task, it has some work effort. According to the magic formula, Work = Duration * Units. Typically, the purpose of a milestone is not to accomplish some work, but to close some phase (i.e. a set of tasks under the summary task) or to check if those tasks are really done.

Let’s say that the editor is the resource who should sign the final review before my article can be published on MPUG’s site. If the editor has to read the whole article, and it will take several hours, then he/she likely needs to separate tasks with some effort, and, of course, duration. On the other hand, if he/she needs only to sign off and approve my article for publication and it will take only a moment, it makes sense to assign him/her to the milestone like this:

Let me show you a more complicated project:

As you can see in the scenario above, we have two summary tasks, and three milestones, one for each phase, as well as one milestone for the whole project. I assigned a resources to each milestone. This does not harm the project plan, or the work effort.

To conclude, you would likely not assign resources to milestones if all tasks in a set leading to the milestone complete the list. In this case, the milestone is automatically considered completed when all the tasks have been, so only thing to do is mark the milestone as 100% done. On the other hand, if a responsible person needs to approve all the tasks in a set once they have been completed, he/she should be assigned to that milestone. Both approaches are correct.

The last thing to consider is if the milestone involves some work, in which case it should have a duration. When you have a duration linked to a milestone, cost will occur. In a “classic” milestone, with zero work and duration, there are no costs.

 

Written by Nenad Trajkovski
MVP - Project Nenad Trajkovski was born in Zagreb in 1963. year. After completion of Faculty of Electrical Engineering, Nenad has started on the development and implementation of enterprise systems (ERP) in companies of various areas (banks, card houses, production companies, auto industry, wholesale businesses, oil companies, and others). He has extensive experience in working with business processes, people and knowledge in information technology and financial accounting activities. Currently, Nenad works as a consultant for the implementation of business systems, and as Project Manager. He is trainer for Project Management and Risk Management in Microsoft Innovation Center in Varaždin. At WinDays08 conference he has been declared as the best speaker, and his session as the best one. He was among TOP 10 speakers in the Microsoft Sinergija 2009 and at the Microsoft Vzija 2009. Shared first place as the best lecturer at KulenDays 2009 and the PMI Forum 2009 in Zagreb. Regular speaker at the Microsoft Community. On WinDays10 conference Nenad was among the top three speakers; at the conference Microsoft Vision 9 in Skopje between the top 5 speakers as well as on Microsoft Synergy 11 which was held in Belgrade. Certified Accountant, PMP (Project Manager Professional), PMI – RMP (Risk Manager Professional), MCP (Microsoft Certified Professional), MCTS – Microsoft Project 2010 (Microsoft Certified Technical Professional).  and MCT (Microsoft Certified Trainer).
Share This Post
Have your say!
00
5 Comments
  1. Assign resources to a milestone? NO! The purpose of a milestone is a point-in-time marker, not a task. If something has resources and work, it’s a task or something else (depending on your methodology.)

    As for setting them up in a separate summary task – why? They are tied to dependencies in real work packages and that’s where they belong. I agree with the practice of starting and ending work packages with milestones – it does add lines to the schedule but gives a clear anchor point for predecessors and successors.

  2. Aside from customers rejecting schedules, etc…
    MSP doesn’t appear to use a Resource’s “Availability” unless the resource has at least 1 min of time assigned to a task. Assigning a person at 0% on the milestone doesn’t allow project to move the Task’s Dates to fit the person’s availability, even in a Fixed Work or Fixed Units task. How to see this:
    1) Set the milestone task to be Type of Fixed Work or Fixed Units
    2) Make a resource called “LimitedEditor” with a Resource Calendar that’s set for vacation (out of the office) throughout September 2018.
    3) In your first example, assign “LimitedEditor” as a resource on the milestone task
    4) The date doesn’t move – but they’re not available to work until October – they won’t be there to approve the milestone.
    If you assign time to them, and the Type is Fixed Work or Fixed Units, the milestone will move to their available date.
    BTW: This all assumes you don’t have “Ignore Resource Calendar” set for the task

  3. Considering that the milestones are not tasks but points of completion of a group of tasks, these should not have assigned resources, but also depends on the styles that some organizations require, for example, some clients prefer that incorporates resource to the milestone to identify who is responsible for ensuring that the task group concludes satisfactorily.

    In my case, I do not usually allocate resources, because even if I assign them, they do not represent effort or cost because they have zero duration.

    Finally, the article has been interesting and useful for me to share with new collaborators who are integrating themselves into the PM role.

  4. Milestones are a special subset of a Task in that they contain zero effort and mark a change in state or transition. The meeting is either complete or it is not …. how much work/cost is consumed in a task with zero duration?

    Best scheduling practices, as noted in the DoD/Aerospace world forbid the practice of resources on milestones. Additionally, the Practice Standard for Scheduling (Published by the Project Management Institute) also says milestone resources are inappropriate.

    Sometimes people confuse the “Responsible Party” with the person doing the work (the resource) and assign a “responsible person” as opposed to a task resource. In my world (generally aerospace) the responsible party is a separate field.

    Yes, the software will allow it … that does not make it a god practice. I would suggest keeping “responsible party” as a separate field.

    Ah, but we do have another issue — “value” For example, payment milestones. I may be building a house and agree to provide a progress payment to the contactor of $25,000 when a specific milestone is closed to 100% (Milestones are either 0% or 100% … I can’t take 30% credit for something of zero duration — it either happened or it didn’t.) It would be other rules in the contract that allow for a partial payment.

    Occasionally, I do see people trying to claim “progress payments” and want to assign 30% to a milestone saying “Well, the foundation is 30% complete.” I believe the better way to handle that is based on the %Complete of an associated summary task.

    In doing so, we are conflating two different measures of %Complete. In Microsoft Project, the value for “%Complete” represents exactly one thing — duration. A 10 day task is 30% complete at the end of day 3. There is no other correct answer. In the event the duration is 30% elapsed and the contract has 75% of the foundation poured and set, this represents the value of “Physical % Complete” (a different field in MS Project), Typically, we’d make a one day task of “Send Progress Payment to Contractor” of duration 1 day (or whatever) and then assign a Cost Resource of $25,000 to that task.

    I have a white paper on “What Percent Complete Should I Be” and it would be my pleasure to provide it for the purpose of continuing the discussion. Please visit the “Resources Tab” on my website for a PDF download. My website is projectpmo (dot) com

    I respect diverse points of view, please keep in mind that assigning dollar values or the like to a milestone produces unique behavior within the software and it may not roll up the way you expect.

  5. A charter or statement of work often specifies executive level milestones. Having a milestone at the end of the detail tasks under a summary is useful for reporting to a program or portfolio manager. To filter for exec level milestones, set milestone resources that include a useful preface, e.g. Ex-Design completed.

    Putting milestones at the top of a schedule for management to find easily causes a forest to dependency lines and can trip up a schedule when not manually marked 100% when appropriate. Better is to provide management a view that uses Group by “Milestones”.

Leave a Reply

Get our FREE Microsoft Project Speed Guide: 10 Essential Time Savers