Ask the Experts: When % Complete Won’t Calculate

Nancy asks, “I have been a project controller for about seven years. I have a problem that I cant figure out. My % Complete column has stopped calculating. Also, the Actual Duration and Remaining Duration are not being updated either. Actual Duration is always zero even though its well into the task. So Remaining Duration equals Duration. What would cause that?”

Answer: This one is really puzzling. After reviewing the MPP file sent, I wasn’t able to see why the % completed doesn’t calculate. I have checked the settings which, are all fine. Then I exported the project into an XML file and re-imported it ( just in case the schedule is corrupt); but this didn’t change the behavior (which is a bummer).

I’ve also noticed that some % completed updates actually work. Task 31, for example, works fine, but Task 3 doesn’t work at all in regards to the % complete. It seems that a combination of settings and corruption could create this effect. So here’s how I suggest you make it work. (I assume this isn’t a Project Server environment, but only an MPP file.)

1. Save the project as an XML file.
2. Open the XML file in Microsoft Project and create a new project.
3. Go to tools | option. Within the Calculate Tab select “Updating Task Status updates Resource Status.”
4. Save the project.

Nancy replies: “Well, thank goodness! It’s in a Project Server environment, so I skipped steps 1 and 2. It still worked. Thank you so much!”

 

 

Next Webinar

Ask the Experts: Making Interim Plans Work for You

Written by Marc Soester
Marc Soester is the Managing Director of i-PMO, an organisation dedicated to successfully implement Microsoft's Enterprise Project Management (EPM) solution throughout Australia. Marc and his team have extensive expertise in the implementation of Microsoft Project Server and Portfolio Server as well as conducting training in Project. He has more then six years of experience implementing EPM solutions and is Australia's first and currently only Project MVP (Most Valuable Professional). You can contact him at marc.soester@i-pmo.com.au.
Share This Post
Have your say!
00
1 Comment
  1. I had the same problem and this solution solved it. Mine was also in Project Server so I did what Nancy did and it worked.

    Thanks!