Reply To: Calendars that span 24 hours

Home Forums Discussion Calendars that span 24 hours Reply To: Calendars that span 24 hours

#107476
Prakash K P
Participant

Please remember if you select 24 hours calendar, your resources will be working 24/7. Since you have two shifts day and night, use the project standard calender for both shifts separately and adjust the hours. If you still want to change your 24 hours calendar to 7 am to 7 am, do the following

1. Go to Project–> Project information
2. Select the calendar as 24 hours calendar
3. Go to Files –> Option –> Schedule, change the default start and end time to 7 AM
4. Change the hours per week value to 168h