Hi Prakash – Good thought.
One change, on any day in the WorkWeek “From” time should be greater or equal to 12 AM and greater than “To” time of the previous shift on the same day. “To” time should be less than or equal to 12 AM and less than “From” time of the next shift on the same day
the end time should be greater than its start time and should be less than or equal to 12 am. Also,
So, I would recommend two create three shift base calendars
a) 7am-7pm base calendar: Work Weeks, Monday – Friday, 7 am – 7 pm
b) 7pm-7am base calendar: Work Weeks, Monday – Friday, 12 am – 7 am, 7 pm – 12 am | Saturday, 12 am – 7 am
c) 7am-7am base calendar: Work Weeks, Monday – Friday, 12 am – 7 am, 7:01 am – 12 am | Saturday, 12 am – 7 am