Hello Drew,
If you have a task that will take 1 day and the work is 16 hours you can allocate the Painter at 200% for that tasks. Project should now schedule 16 hours for 1 day duration provided you have your calendars set up correctly, eg. 8 hour working day.
I would do this allocation at the task level and let the application show that I need 2 painters for that task over that duration.
Hope this helps.