Reply To: How to manage complicated resource interactions

Home Forums Discussion How to manage complicated resource interactions Reply To: How to manage complicated resource interactions

#114278
Larry Christofaro
Participant

Interesting question. This is a response based on what you wrote, but let me toss some thoughts at you:
1. Assign both the department and part to the same task but mark the task as effort driven-no. This will assign both full-time
2. Now you can validate (manually or using Microsoft leveling) whether the department/part is overbooked (two places/parts at the same time.
3. Total work will be overstated. You could group your resources into either Department or Part, and then check total work using the resource sheet (not Gantt chart)
Hope that helps…Larry