Reply To: Project server 2010, New Timesheet view created, how to see it and activate it?

Home Forums Discussion Project server 2010, New Timesheet view created, how to see it and activate it? Reply To: Project server 2010, New Timesheet view created, how to see it and activate it?

#114702
Larry Christofaro
Participant

George, well at this point I’m at a loss as it is a very simple solution. So can I ask, are others able to see the view and you are the only one who can’t, or is your colleague the only person who can see the view? Did you include all categories in the view…just in case? If you create another timesheet view, does this have the same affect? Are there other views from other view types that act the same way? What if you just recreate the same view (delete it and create a new one)?

I’m not leading to any other solution but certainly curious as to what is going on. Trying to see if it is a one time happening or if there is some consistent behavior. Let me know what you find out.

Thanks…Larry