I believe the short answer is no – the calculation for duration is hard coded and based on duration, not work values.
Citing MS –
“Project uses the following calculation:
Percent Complete = Actual Duration / Duration”
Couldn’t you instead have your team populate the Actual Duration + Remaining Duration fields to establish your Duration.That would then satisfy the sync requirement for % complete.