Reply To: Project Pro 2013 sync to SharePoint 2013 – Actuals and Remaining Work sync?

Home Forums Discussion Project Pro 2013 sync to SharePoint 2013 – Actuals and Remaining Work sync? Reply To: Project Pro 2013 sync to SharePoint 2013 – Actuals and Remaining Work sync?

#115528
Alicia Zagar
Participant

I believe the short answer is no – the calculation for duration is hard coded and based on duration, not work values.

Citing MS –
“Project uses the following calculation:
Percent Complete = Actual Duration / Duration”

Couldn’t you instead have your team populate the Actual Duration + Remaining Duration fields to establish your Duration.That would then satisfy the sync requirement for % complete.