Loading...
Quick Links

Reply To: Project Pro 2013 sync to SharePoint 2013 – Actuals and Remaining Work sync?

Home Forums Discussion Project Pro 2013 sync to SharePoint 2013 – Actuals and Remaining Work sync? Reply To: Project Pro 2013 sync to SharePoint 2013 – Actuals and Remaining Work sync?

#115670
LD
Participant

Thanks you for the reply. To further explain the issue it is related to a specific message that appears when trying to add the Actual Work and Remaining Work fields to the sync, “The value of the following fields are depended on each other in Microsoft Project. In order to maintain the dependency, only the last field (% Complete) will be synched between SharePoint and Microsoft Project. The other fields (Actual Work) will have their value controlled by the value for % Complete.” Looking for a way that entry of projected and actual work hours can drive the % complete rather than % complete drive the actual work.