Loading...
Quick Links

Reply To: Update only extending, and not moving, tasks with links automatically

Home Forums Discussion Update only extending, and not moving, tasks with links automatically Reply To: Update only extending, and not moving, tasks with links automatically

#116215
Sai PrasadSai Prasad
Participant
  • Community Leader
  • Forum Pro

When the task is delayed/extended, Project will only adjust the start date of its successor; assuming it is FS dependency. But you want the duration of the 40 tasks to expand/reduce when you move the linked milestone is moved which is not possible.