Reply To: Project server 2010, New Timesheet view created, how to see it and activate it?

Home Forums Discussion Project server 2010, New Timesheet view created, how to see it and activate it? Reply To: Project server 2010, New Timesheet view created, how to see it and activate it?

#116240
Richard Frisby
Participant

I’m with Larry on this one. Check the view itself and make sure it is allowed to be used by the category you are a member of. The other user may be assigned in other categories in addition to the one in common with you, one of which may allow access to that view.