You didn’t state whether you are referring to MS Project reports or Project Server. If you are referring to MS Project (I’m also assuming 2013), there are a lot of videos and MS Project books that include the new reports discussion. These do not require technical expertise which may be why you don’t see specific examples. For your Cash Flow report in MS Project, the total cumulative lines use Cumulative fields. For your specific request you don’t have a Baseline cumulative cost, all you have is Baseline Cumulative Work. Cumulative Cost would give you the Actual and ETC line. There are third party reporting tools out there but I don’t know off the top of my head if one of them will give you what you want. There are also many third party options for Project Server if this is what you are referring to. Good luck…