Reply To: How to create a task that automatically spans the entire project duration?

Home Forums Discussion How to create a task that automatically spans the entire project duration? Reply To: How to create a task that automatically spans the entire project duration?

#119227
Chris Rose
Guest

Yes, this technique does work, and has been around for a while. One caveat is this technique with Project Server use. We experienced problems with project files that contained this “hammock” task using Server. Stand alone is no issue. Just something to be aware of.