Reply To: Resource allocation to the tasks:

Home Forums Discussion Resource allocation to the tasks: Reply To: Resource allocation to the tasks:

#126647
Neeraj
Guest

Let me put it this horses ,
I have an inventory of two types of resources,say horses and carts.

In a given task, I need an assembly of one horse and one cart to transport goods from point A to B.
Also let’s assume that either of the two alone cannot be used.

In such a scenario,the time for which a horse and a cart is used for a particular task would be the same I.e. 2 days. When I attempt to record the actual work for both these resources, it should show the same time consumed for the horse and the cart.

Currently, I am getting the actual work split up in to 1 day each,which simply isn’t the case for the task mentioned above.

Hope this gives you a better picture of my problem.