Loading...
Quick Links

Reply To: Baseline and Baseline 1-10

Home Forums Discussion Baseline and Baseline 1-10 Reply To: Baseline and Baseline 1-10

#127978

Larry, exactly what I was looking for, thank you. So just for adding additional tasks to the project, I can safely add them to Baseline 0 and use the rest the way you said. That makes more sense and I hadn’t considered running out of baselines.

If I don’t have resources in my projects, is there any problem with copying/pasting the start and finish date into the baseline start and baseline finish date columns? That essentially is the same thing as adding them to my Baseline 0, correct?