Juliano
Guest

Thank you for your reply
I work on oil industry and it involves a well planned schedule due the costs involved.
Sometimes maintenance is necessary, where we need to Shutdown a gas or water train (partially shutdown the plant) and the client allows us some specific time for completion the maintenance. So we cannot have delays – This is why I had precise 48 hours on my example.
Juliano