Reply To: Individual Project Managers in a Master Project

Home Forums Discussion Individual Project Managers in a Master Project Reply To: Individual Project Managers in a Master Project

#135378
Randy Johns
Guest

Hi Larry,

I did have to publish the sub-projects in order to insert them into the master project. That worked perfectly. What I am struggling with now is that once the sub-projects are inserted into the master project, they no longer are available to me to select in the Project Center; I can only see the newly created master project. How can I get to the individual sub-projects in PWA to assign individual owners of the sub-projects?