Reply To: HOW TO CALCULATE TASKS THAT INVOLVE SHIFTS

Home Forums Discussion HOW TO CALCULATE TASKS THAT INVOLVE SHIFTS Reply To: HOW TO CALCULATE TASKS THAT INVOLVE SHIFTS

#137706
Anthony Warrix
Participant

Juliano.
I was also working on a 24 hour task when I read your post.

1. Set project calendar to 24 hours
2. Set timescale middle tier = days bottom tier = hours
3. Generate tasks for the appropriate shifts (I used 3 – 8 hour shifts)
4. assign resources
Summary:
48 hour task started at Friday at 3:30pm and ended on Sunday at 3:30pm = 48hours

Send me your email and I’ll send you the project plan (2010)

Anthony