Thanks for the quick response!

We’re trying to have a schedule with tasks, duration,start, end dates and dont enter any resources (as there are too many :))While updating progress, we just enter % complete. My concern is since there are no resources, there is no work/cost, so what kind of reports can I have?
I can at best see tasks slipping, late tasks, etc. Is this the right way? Or should we use physical % complete and work column? I cant get EVM, s-curve, burndown or other reports-isnt it? what should I do to have these?

Please let me know the best way to update progress where we dont enter resources.