Reply To: Highlight tasks which take place on the weekend

Home Forums Discussion Highlight tasks which take place on the weekend Reply To: Highlight tasks which take place on the weekend

#160793

Fastest way to do it, I guess, would be as follows:
Change “Calendar” to Standard and choose a dark nonworking time color, then check the Gantt graph…
See: http://office.microsoft.com/en-us/project-help/timescale-dialog-box-non-working-time-tab-HP001226008.aspx