Reply To: Project 2013 text wrap issue

Home Forums Discussion Project 2013 text wrap issue Reply To: Project 2013 text wrap issue

#160882
Larry Christofaro
Participant

Common rant but there is an answer. Right click on the Task Name column header and select Wrap Text. This column defaults to wrapping the text but you can turn it off. Note that you will need to unwrap all the current tasks one more time but then they will stay unwrapped. You can do this easily by selecting the entire table (selects all rows) and then collapsing the row bar of one of the tasks. Hope this helps…