Reply To: Highlight tasks which take place on the weekend

Home Forums Discussion Highlight tasks which take place on the weekend Reply To: Highlight tasks which take place on the weekend

#162814

If you have already modified and used the Standard base calendar as the project calendar, then you can create another calendar, for example, Standard_with_NonWorking and use it to draw nonworking times in the Gantt as explained above.