Home › Forums › Discussion › Highlight tasks which take place on the weekend › Reply To: Highlight tasks which take place on the weekend
If you have already modified and used the Standard base calendar as the project calendar, then you can create another calendar, for example, Standard_with_NonWorking and use it to draw nonworking times in the Gantt as explained above.