Good question. I know there is/was a bug that under certain circumstances, Project will not calculate 100% but I thought it was in relationship to marking tasks as scheduled (or something like that). Try changing remaining duration to 0 and see if that will work. I can’t seem to recreate it right now. Hope that helps…