Rebaseline is due to approved change request which includes scope, time, cost and quality impact. The change request are approved if there are no options to meet the original baseline.

When updating the baseline, ask yourself : “Is all the task approved again (or) only selected tasks are approved?”. This help you to decide whether to select either “Entire Project” or “Selected Tasks” in Set Baseline dialog