Loading...
Quick Links

Reply To: when to rebaseline and when not to?

Home Forums Discussion when to rebaseline and when not to? Reply To: when to rebaseline and when not to?

#184260
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Interim Plan is used to backup baseline information or backup the current Start and Finish date. For instance, before updating the baseline if you need to have a backup of the current baseline, you copy Baseline to Baseline 1 (… Baseline 10) by select Interim Plan in Set Baseline dialog and selecting Copy: Baseline and Into: Baseline1. Another instance the interim plan will be useful is when you want to see the effect of the recent update on the current start and finish date. You can copy Start/Finish to Start1/Finish1, update the estimates/actuals, and compare the current Start, Finish with Start1 and Finish1.