Reply To: MS Project 2013: Customizing Calendar View (filter to specific user)

Home Forums Discussion MS Project 2013: Customizing Calendar View (filter to specific user) Reply To: MS Project 2013: Customizing Calendar View (filter to specific user)

#203893
Michael Sutherland
Guest

Neil

As long as you have assigned resources to each task, you can filter the calendar view, go to “View” select “Calendar” then in the
‘Data” section select the “Filter” pull down list and select the “Using Resources” option. Note: this is in Project 2010 so may be different for 2013.